Focus Area: Infrastructure (Engineering)
Staff Contact: Mary Jaeger / Nate Baldwin
Subject: Report on projects and locations included in the 2025 Street Preservation Program, 3-P-000-25
________________________________________________________________________________
TITLE:
title
Report on projects and locations included in the 2025 Street Preservation Program, PN 3-P-000-25.
Body
________________________________________________________________________________
Summary:
The 2025 Street Preservation Program will include the following projects:
K-7 Highway Arterial Mill and Overlay Project - Loula Street to Harold Street
143rd Street Arterial Mill and Overlay Project - Mur-Len Road to Black Bob Road
Lakeshore Drive Arterial Mill and Overlay Project - Dennis Avenue to 135th Street
167th Street Improvements Project - Hedge Lane to I-35 Highway
Clare Road Arterial Mill and Overlay Project - 114th Street to College Boulevard
Valley Parkway Arterial Mill and Overlay Project - Cedar Creek Parkway to 103rd Terrace
Local & Collector Street Mill and Overlay Projects (LCMO) -See street list exhibit for LCMO Group A and Group B construction locations. The projects include 99 street locations totaling 32 lane miles.
Micro Surface Project - See street list exhibit and map for MAQS Micro Surface locations. The project includes 161 street locations, totaling 50 lane miles.
Street Maintenance Curb Replacement Project - Removal and replacement of approximately 25,000 linear feet of deteriorated curb and gutter by Street Maintenance Concrete Crews in multiple locations throughout Olathe.
Street Maintenance Crack Sealing Project - Crack sealing materials for approximately 250 lane miles to be applied throughout the city by Street Maintenance Crews.
Design costs for 2026 Arterial Mill and Overlay Projects will utilize 2025 Street Preservation funding. The following projects are currently included, but are not limited to:
135th Street, Mur-Len Road to Pflumm Road
Old 56 Highway, Chestnut Street to Mahaffie Street
Kansas Avenue, Spruce Street to Harold Street
119th Street, Sunset Street to Ridgeview Road
Black Bob Road, 153rd Terrace to 151st Street
Alternate Streets for the LCMO and MAQS Micro Surface Projects are included in the Exhibit B Street Lists document. The alternate streets are not included in the total number of primary streets and lane miles listed above with each project. These alternate streets are authorized for construction but not currently scheduled for construction. Upon completion of the scheduled primary streets, if adequate funding remains to construct some or all alternate streets, these streets may be added for construction by a change order to an existing project or bid as a separate project.
________________________________________________________________________________
Financial Impact:
Funding for the 2025 Street Preservation Program, as approved in the 2025-2029 CIP, includes:
CIP Fund (Cash) $ 2,800,000
Transportation Sales Tax $18,470,000
Total: $21,270,000
________________________________________________________________________________
Action Needed:
No action is requested at this time. Staff will return to Council for approval of construction contracts for the projects listed above.
________________________________________________________________________________
Attachment(s):
A. Project Location Map
B. Street Lists Exhibit