Title: Consideration of Resolution No. 25-1090 authorizing the Fire Station No. 4 Replacement Project, PN 6-C-022-25.
Staff Contact: Jeff DeGraffenreid, Mary Jaeger, Zach Hardy, Laura Gagliano
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Resolution

Focus Area: Fire, Infrastructure (Facilities)

Staff Contact: Jeff DeGraffenreid / Mary Jaeger / Zach Hardy / Laura Gagliano

Subject: Authorization of the Fire Station No. 4 Replacement Project, PN 6-C-022-25.

________________________________________________________________________________

TITLE:

title

Consideration of Resolution No. 25-1090 authorizing the Fire Station No. 4 Replacement Project, PN 6-C-022-25.

Body

________________________________________________________________________________

Summary:

This project provides for the design and construction of a new Fire Station No. 4.

 

Fire Station #4 was built in 1971. Multiple renovations have occurred in an attempt to extend the life of the building. Centrally located in the city, north of West Santa Fe on the east side of North Mur Len, this is one of the busiest stations in Johnson County. This facility was built to house one fire apparatus which no longer meets the needs of the City. In the future, Fire Station #4 will be staffed as a dual-company fire station to best meet the needs of the area and comply with requirements that directly impact the community's ISO rating. The current station does not provide enough space to reconfigure the floor plan to address staffing and apparatus needs to service this area of the community. The new station will be constructed on the same property after demolition of the existing structure. 

 

The estimated cost for this project is $16,500,00 and includes the preliminary and final design, staff time, construction, inspections, ancillary costs, construction and contingency.

 

The planning and design phase of this project is anticipated to begin in Fall 2025 and conclude in Fall 2026. Construction is anticipated to begin in November of 2026 and be complete in February of 2028.

________________________________________________________________________________

Financial Impact:

Funding for the Fire Station No. 4 Replacement Project, as approved in the 2026-2030 Capital Improvement Plan, is $16,500,000 of General Obligation Bonds.

________________________________________________________________________________

Action Needed:

Approval of Resolution No. 25-1090 authorizing the Fire Station No. 4 Replacement Project, PN 6-C-022-25.

________________________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Resolution