Title: Consideration of an Agreement with Johnson County for construction of the Stream Rehabilitation Near 125th Terrace project, PN 2-R-001-24.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Agreement

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Agreement with Johnson County for construction of the Stream Rehabilitation Near 125th Terrace project, PN 2-R-001-24

________________________________________________________________________________

TITLE:

title

Consideration of an Agreement with Johnson County for construction of the Stream Rehabilitation Near 125th Terrace project, PN 2-R-001-24.

Body

________________________________________________________________________________

Summary:

This project will improve and stabilize 325 feet of open channel in the Northridge subdivision, south of 125th Street.  Attachment A shows the location of this project.

 

This project was chosen to be funded by Johnson County’s Stormwater Management Advisory Council (SMAC) program in the amount of up to $150,000 (50% of a maximum of $300,000) for design and construction of the project.  On August 20, 2024, City Council approved a construction agreement with VF Anderson Builders, LLC, for construction of this project.  In order for the City to accept County funding for construction, the City must approve this construction agreement with the Johnson County SMAC program.

 

Construction is scheduled to begin September 2024 and be completed Fall 2024.

________________________________________________________________________________

Financial Impact:

Stormwater Fund (2023)                                                                                                         $  49,500

Stormwater Fund (2024)                                                                                                         $175,000

                     SMAC Reimbursement                                                                                                         $150,000

                     Total                                                                                                                                                                        $374,500

________________________________________________________________________________

Action Needed:

Approval of an Agreement with Johnson County for construction of the Stream Rehabilitation Near 125th Terrace project, PN 2-R-001-24

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Project Fact Sheet

C.                     Agreement