Department: Public Works
Staff Contact: Mary Jaeger / Beth Wright
Subject: Contract award to VF Anderson Builders for construction of the Woodland Road, K-10 to College Boulevard, Improvements Project, PN 3-C-041-18.
________________________________________________________________________________
Item Description:
title
Consideration of Engineer’s Estimate, acceptance of bids and award of contract to VF Anderson Builders, LLC for construction of the Woodland Road, K-10 to College Boulevard, Improvements Project, PN 3-C-041-18..
________________________________________________________________________________
Summary:
On January 7, 2020, three (3) bids were received and opened for the above referenced project. The bids ranged from $9,559,901.85 to $11,069,000.00 with the Engineer’s Estimate at $10,569,398.50. VF Anderson Builders, LLC submitted the low and responsible bid in the amount of $9,559,901.85. The following is a tabulation of the bids received:
VF Anderson Builders, LLC $ 9,559,901.85
Miles Excavating $ 9,884,818.62
Engineer’s Estimate $10,569,398.50
McAnany Construction, Inc $11,069,000.00
This project will improve Woodland Road to a four-lane divided arterial roadway between K-10 Highway and College Boulevard. Improvements will include pavement reconstruction, curb and gutter, turn lanes, medians, landscaping, on-street bike lanes, sidewalks, storm sewer, and new streetlights.
Construction is tentatively scheduled to begin in February 2020 and to be completed in early 2021.
________________________________________________________________________________
Financial Impact:
Funding for the Woodland Road, K-10 to College Boulevard, Improvements Project, as approved in the 2019 Capital Improvements Plan, includes:
GO Bonds $13,076,000
Total $13,076,000
________________________________________________________________________________
Action Needed:
Approval of Engineer’s Estimate, acceptance of bids and award of contract to VF Anderson Builders, LLC for construction of the Woodland Road, K-10 to College Boulevard, Improvements Project, PN 3-C-041-18.