File #: G25-5306   
Type: Council Consent Status: Passed
File created: 9/3/2025 In control: City Council
On agenda: 10/7/2025 Final action: 10/7/2025
Title: Consideration of an Agreement with Infrastructure Solutions LLC for design-build services for the Kansas Ave & Poplar St Waterline Rehabilitation, PN 5-R-001-25, the Cherry St Waterline Rehabilitation, PN 5-R-003-25, and the Town of Olathe Block 46 Sanitary Sewer Rehabilitation Projects, PN 1-R-101-25.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. DBIA Agreement

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Contract with Infrastructure Solutions LLC for design-build services for the Kansas Ave & Poplar St Waterline Rehabilitation, PN 5-R-001-25, the Cherry St Waterline Rehabilitation, PN 5-R-003-25, and the Town of Olathe Block 46 Sanitary Sewer Rehabilitation Projects, PN 1-R-101-25.

________________________________________________________________________________

TITLE:

title

Consideration of an Agreement with Infrastructure Solutions LLC for design-build services for the Kansas Ave & Poplar St Waterline Rehabilitation, PN 5-R-001-25, the Cherry St Waterline Rehabilitation, PN 5-R-003-25, and the Town of Olathe Block 46 Sanitary Sewer Rehabilitation Projects, PN 1-R-101-25.

Body

________________________________________________________________________________

Summary:

These projects will replace approximately 1,500 feet of waterline and 750 feet of sanitary sewer main in Downtown Olathe around areas of anticipated redevelopment ahead of their construction. Waterlines will be replaced on the west side of Kansas Avenue north of Santa Fe Street up to Spruce Street as well as along the west side of Cherry Street south of Santa Fe Street to Park Street. Sanitary sewer mains will be replaced around Chestnut Street south of Santa Fe Street.

A Request for Qualifications for Design-Build Services for design and construction of this project was released on April 11, 2025. Two (2) firms responded to this request and Infrastructure Solutions LLC was selected based on the submitted qualifications. The proposed agreement with Infrastructure Solutions, LLC. is a Guaranteed Maximum Price package totaling $1,326,769.43 for construction of the projects.

The following is the tentative construction schedule and sequencing of the projects:

Kansas Ave & Poplar St Waterline Rehabilitation:                                           Oct 2025 - Nov 2025

Town of Olathe Block 46 Sanitary Sewer Rehabilitation:          Dec 2025 - Jan 2026

Cherry St Waterline Rehabilitation:                                                                           Mar 2026 - Apr 2026

________________________________________________________________________________

Financial Impact:

Funding for the Kansas Ave & Poplar St Waterline Rehabilitation, Cherry St Waterline Rehabilitation, and Town of Olathe Block 46 Sanitary Sewer Rehabilitation Projects is from the following sources:

 

Waterline Rehabilitation (5-R-000-25):

                                          Water & Sewer Fund                                                               $3,400,650

                                          Revenue Bonds                                                                                    $2,704,350

                                          Total                                                                                                                              $6,105,000

 

Neighborhood Sanitary Sewer Improvements (1-R-100-25):

                                          Water and Sewer Fund                                                               $1,724,800

                                          Total                                                                                                                              $1,724,800

________________________________________________________________________________

Action Needed:

Approval of an Agreement with Infrastructure Solutions, LLC for design-build services for the Kansas Ave & Poplar St Waterline Rehabilitation, PN 5-R-001-25, the Cherry St Waterline Rehabilitation, PN 5-R-003-25, and the Town of Olathe Block 46 Sanitary Sewer Rehabilitation Projects, PN 1-R-101-25.

________________________________________________________________________________