City of Olathe header
To visit archives prior to April 2024 please click here.
File #: G24-4125   
Type: Reports Status: Agenda Ready
File created: 12/20/2023 In control: City Council
On agenda: 1/9/2024 Final action:
Title: Report on the authorization of the Quivira Road, 143rd to 151st, Improvements Project, PN 3-C-011-24.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. CIP Sheet

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Report on the authorization of the Quivira Road, 143rd to 151st, Improvements Project, PN 3-C-011-24.

________________________________________________________________________________

TITLE:

title

Report on the authorization of the Quivira Road, 143rd to 151st, Improvements Project, PN 3-C-011-24.

Body

________________________________________________________________________________

Summary:

This project is needed to address safety and capacity concerns in the area.  The project will improve Quivira Road from 143rd Street to 151st Street from a 2-lane unimproved roadway to a 2-lane divided arterial section with turn lanes.  Improvements will include pavement construction, curb and gutter, medians, streetlights, sidewalk and sidepath, bike lanes and storm sewers.

 

The estimated cost for this project is $17,429,000 including preliminary and final design, utility relocations, staff time, land acquisition, permitting, construction and inspection.

 

This project is tentatively scheduled for design in 2024/2025, land acquisition and utility relocations in 2025, and construction in 2026.

________________________________________________________________________________

Financial Impact:

Funding for the Quivira Road, 143rd to 151st, Improvements Project, as approved in the 2024-2028 Capital Improvement Plan, includes:                     

                     

GO Bonds                                                                                                         $13,853,091

Federal (STBG)                                                                                    $  3,575,909

Total                                                                                                    $17,429,000

________________________________________________________________________________

Action Needed:

No action is requested at this time.  Staff will return to Council on January 23, 2024, to request approval for authorization of the project.

________________________________________________________________________________

Attachment(s):

A.  Project Location Map

B.  Project Fact Sheet

C.  CIP Sheet