Focus Area: Infrastructure (Engineering)
Staff Contact: Mary Jaeger / Nate Baldwin
Subject: Change Order No. 5 with Pyramid Contractors, Inc. for the 119th Street, Woodland to Northgate, Improvements Project, PN 3-C-024-21.
________________________________________________________________________________
Title:
title
Consideration of Change Order No. 5 with Pyramid Contractors, Inc. for construction of the 119th Street, Woodland to Northgate, Improvements Project, PN 3-C-024-21.
Body
________________________________________________________________________________
Summary:
This project is needed to provide a missing link of 119th Street between Woodland Road and Northgate, giving total transportation connectivity of 119th Street from K-7 Highway to I-35, reducing congestion on adjacent arterials, and promoting commercial growth and development along the 119th Street corridor. The Project will include a new 4-lane divided arterial section of 119th Street between Woodland and Northgate, as well as intersection improvements at Lone Elm Road and 119th Street, Iowa and 119th Street, Woodland Road and 119th Street, with a new roundabout at 119th Street and Northgate Street. The Project will also include a bridge that spans the BNSF Railroad and Mill Creek. The Project will provide pedestrian accommodations and a connection from 119th Street to the Gary Haller Trail.
This change order will address emergency storm sewer repairs along the south side of 119th Street, east of Sunset and adjacent to the current project area. There is a large corrugated metal pipe (CMP) failure and a growing sinkhole. The total of this Change Order No. 5 is $667,829.00.
It is anticipated the structural repair of the storm sewer would commence in early 2026 upon approval of this change order.
________________________________________________________________________________
Financial Impact:
Funding for the 119th Street, Woodland to Northgate, Improvements Project, includes:
Johnson County CARS $ 4,350,000
GO Bonds $45,340,000
Total $49,690,000
________________________________________________________________________________
Action Needed:
Approval of Change Order No. 5 with Pyramid Contractors, Inc. for construction of the 119th Street, Woodland to Northgate, Improvements Project, PN 3-C-024-21.
________________________________________________________________________________
Attachment(s):
A. Project Location Map
B. Project Fact Sheet
C. Change Order No. 5