File #: G24-4259   
Type: Council Consent Status: Passed
File created: 3/4/2024 In control: City Council
On agenda: 3/19/2024 Final action: 3/19/2024
Title: Consideration of Engineer's Estimate, acceptance of bids and award of contract to Superior Bowen Asphalt Company, LLC for construction of the Ridgeview Road (N) Arterial Mill and Overlay Project, PN 3-P-001-24.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Construction Agreement, 4. D. Engineer's Estimate and Affidavit of Estimate

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Contract with Superior Bowen Asphalt Company, LLC for construction of the Ridgeview Road (N) Arterial Mill and Overlay Project, PN 3-P-001-24.

________________________________________________________________________________

TITLE:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Superior Bowen Asphalt Company, LLC for construction of the Ridgeview Road (N) Arterial Mill and Overlay Project, PN 3-P-001-24.

Body

________________________________________________________________________________

Summary:

On February 26, 2024, two (2) bids were received and opened for the above referenced project. The bids ranged from $4,413,473.18 to $4,638,200.71 with the Engineer’s Estimate at $5,637,937.50. Superior Bowen Asphalt Company, LLC submitted the low and responsible bid in the amount of $4,413,473.18. The following is a tabulation of the bids received:

 

Superior Bowen Asphalt Company, LLC                                          $ 4,413,473.18

McAnany Construction, Inc.                                                               $ 4,638,200.71

Engineer’s Estimate                                                                                                         $ 5,637,937.50

 

This Street Preservation project will provide a 2” depth mill and asphalt overlay on Ridgeview Road from 119th Street to K-10. This project will also include asphalt base repair, concrete curb and sidewalk replacement, installation of ADA compliant sidewalk ramps, installation of 8’-10’ wide shared use path, placement of pavement markings and storm sewer improvements.

 

Construction is tentatively scheduled to begin in Spring 2024 and tentatively scheduled to be completed in Fall 2024.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2024 Street Preservation Program. Funding for the 2024 Street Preservation Program, as approved in the 2024-2028 Capital Improvement Plan, includes:    

 

CIP Fund (Cash)                                                                                                         $   2,800,000

Street Maintenance Sales Tax                                                               $ 20,160,000

Total                                                                                                                                                   $ 22,960,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to Superior Bowen Asphalt Company, LLC for construction of the Ridgeview Road (N) Arterial Mill and Overlay Project, PN 3-P-001-24.

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Project Fact Sheet

C.                     Construction Agreement

D.                     Engineer’s Estimate and Affidavit of Estimate