File #: G24-4457   
Type: Discussion Item Status: Agenda Ready
File created: 6/4/2024 In control: City Council
On agenda: 6/18/2024 Final action:
Title: Discussion of the Fire Station No. 9 project, PN 6-C-013-23.
Staff Contact: Jeff DeGraffenreid, Mary Jaeger, Jeff Blakeman
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet

Focus Area: Infrastructure (Facilities Management), Fire

Staff Contact: Mary Jaeger / Jeff DeGraffenreid / Jeff Blakeman

Subject: This presentation and discussion will provide Council with an update on the planning and design for the Fire Station No. 9 project.

________________________________________________________________________________

TITLE:

title

 

Discussion of the Fire Station No. 9 project, PN 6-C-013-23.

 

Body

________________________________________________________________________________

Summary:

The Fire Station No. 9 project has been approved in the 2023 CIP and the 2024 CIP.  This project is for a new single company fire station to be constructed on City owned property on the north side of College Boulevard approximately 1,500 feet west of Woodland Road. 

 

Agreements with Finkle + Williams for the design of the project and with JE Dunn Construction for construction management services were approved on November 21, 2023.  Upon the award of contract to Finkle + Williams, staff immediately began working with Finkle + Williams on the initial space programming, the building and site planning, and the massing and aesthetics for the fire station.

 

Tonight, City staff and representatives with Finkle + Williams will lead a presentation on the current status of the project design.  This presentation will provide Council with an overview of the process leading to the development of the concept design for the fire station, and will focus discussion on the building massing, building elevations, and suggested materials proposed for the exterior of the fire station.

________________________________________________________________________________

Financial Impact:

Funding for the Fire Station No. 9 project, as approved in the 2024-2028 Capital Improvement Plan, is $14,450,000 of General Obligation Bonds.

________________________________________________________________________________

Action Needed:

Staff requests the City Council provide feedback and direction related to the current design proposed for Fire Station No. 9.