Department: Public Works
Staff Contact: Mary Jaeger / Beth Wright
Subject: Authorization of the Pflumm Road, 143rd to 151st, Improvements Project, PN 3-C-114-20.
________________________________________________________________________________
Item Description:
title
Consideration of Resolution No. 20-1016 authorizing funding for Pflumm Road, 143rd to 151st, Improvements Project, PN 3-C-114-20.
________________________________________________________________________________
Summary:
This project is needed to address capacity and safety concerns in the area.
This project will improve Pflumm Road to a four-lane divided arterial roadway between 143rd Street and 151st Street. Also included will be geometric improvements at both intersections and a new traffic signal at 151st & Pflumm. Improvements will include storm sewer, medians, curb and gutter, new streetlights, on-street bike lanes, sidewalks and all other work necessary to complete the project.
The estimated cost for this project is $18,715,000. This includes preliminary and final design, utility relocation, survey, staff time, construction, construction inspection and land acquisition.
This project is tentatively scheduled for design in 2020, land acquisition in 2020/2021, utility relocations in 2021 and construction in 2022.
________________________________________________________________________________
Financial Impact:
Funding for the Pflumm Road, 143rd to 151st, Improvements Project includes:
CARS $ 2,000,000
Federal (STP) $ 1,500,000
GO Bonds $15,215,000
Total $18,715,000
________________________________________________________________________________
Action Needed:
Approval of Resolution No. 20-1016 authorizing funding for Pflumm Road, 143rd to 151st, Improvements Project, PN 3-C-114-20.