City of Olathe header
File #: G23-3629   
Type: Reports Status: Agenda Ready
File created: 3/7/2023 In control: City Council
On agenda: 3/21/2023 Final action:
Title: Report on the authorization of the new Animal Shelter project, PN 6-C-007-23.
Staff Contact: Mary Jaeger, Beth Wright, Robert Rives
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. 2023 CIP Project Sheet

Focus Area: Infrastructure (Facilities Management), Quality of Life

Staff Contact: Mary Jaeger / Beth Wright / Robert Rives

Subject: Report on the authorization of the new Animal Shelter project, PN 6-C-007-23.

______________________________________________________________________

Item Description:

title

Report on the authorization of the new Animal Shelter project, PN 6-C-007-23.

Body

______________________________________________________________________

Summary:

This project is for the planning, design, and construction of a replacement animal shelter facility located at 1432 W. Ironwood Street, near the Robinson administration facility, within the small Ironwoods building.

 

The Animal Shelter project is included in the approved 2023-2027 Capitol Improvement Plan. The total project budget is identified at $4,630,000. The approved 2023 CIP includes $400,00 of general obligation bond funding. This initial funding of the project will allow staff to proceed with the planning and design of the project.

 

The current facility has operated since its construction in 1988 without any major additions or renovations. This facility has been experiencing chronic space shortages, high maintenance costs and inadequate facilities for proper animal living conditions and staff working environment. With a new facility, the city is looking to provide high quality animal health and housing facilities and staff working environment for the next 15-20 years with options for expansion to accommodate projected city growth.

 

The initial scope of services for this project will be an assessment of the proposed facility, projected future needs of animal control services, design concept development and development of construction documents.

 

Staff will return on April 4, 2023, requesting initial funding authorization in the amount of $400,000. Staff also anticipates returning to the City Council in January 2024 to request full funding of the project.

______________________________________________________________________

Financial Impact:

Initial funding for the Animal Shelter project, as proposed in the 2023-2027 Capital Improvement Plan, is $400,000 of General Obligation Bonds. 

______________________________________________________________________

Action Needed:

No action is requested at this time. Staff will return to Council on April 4, 2023, to request approval to authorize the project.

______________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. 2023 CIP Project Sheet