File #: G25-5245   
Type: Council Consent Status: Agenda Ready
File created: 8/6/2025 In control: City Council
On agenda: 8/19/2025 Final action:
Title: Consideration of a Utility Agreement with Evergy Metro, Inc. for the Quivira Road, 143rd to 151st, Improvement Project, PN 3-C-011-24.
Staff Contact: Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Utility Agreement

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Utility Agreement with Evergy Metro, Inc. for the Quivira Road, 143rd to 151st, Improvement Project, PN 3-C-011-24.

________________________________________________________________________________

TITLE:

title

Consideration of a Utility Agreement with Evergy Metro, Inc. for the Quivira Road, 143rd to 151st, Improvement Project, PN 3-C-011-24.

Body

________________________________________________________________________________

Summary:

This project is needed to address safety and capacity concerns in the area.  The project will improve Quivira Road from 143rd Street to 151st Street from a 2-lane unimproved roadway to a 2-lane divided arterial section with turn lanes.  Improvements will include pavement construction, curb and gutter, medians, streetlights, sidewalk and sidepath, bike lanes and storm sewers.

 

This agreement is in place to allow the City of Olathe to reimburse Evergy Metro, Inc. for the utility relocation required for this project. Olathe’s cost for the relocation, estimated by Evergy Metro, Inc. is $450,092.25. This estimate reflects relocation of power poles and lines and is 26.51% of the overall cost of the relocation ($1,698,021.44). This estimate includes materials, labor, and other costs necessary to complete the relocation.

 

The relocation of Evergy facilities is tentatively scheduled to begin September 2025 and be completed by January 2026.

 

This project is currently in the utility relocation phase and construction is tentatively scheduled to begin in Spring 2026.

________________________________________________________________________________

Financial Impact:

Funding for the Quivira Road, 143rd to 151st, Improvements Project, as approved in the 2025-2029 Capital Improvement Plan, includes:                     

                     

GO Bonds                                                                                                         $13,853,091

Federal (STBG)                                                                                    $  3,575,909

Total                                                                                                    $17,429,000

________________________________________________________________________________

Action Needed:

Approval of a Utility Agreement with Evergy Metro, Inc. for the Quivira Road, 143rd to 151st, Improvement Project, PN 3-C-011-24.

________________________________________________________________________________