File #: G24-4576   
Type: Council Consent Status: Passed
File created: 8/8/2024 In control: City Council
On agenda: 8/20/2024 Final action: 8/20/2024
Title: Consideration of Change Order No. 2 to the contract with Crossland Heavy Contractors, Inc. for construction of the Black Bob Pump Station Site and Piping Improvements Project, PN 5-RF-001-22.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Change Order No. 2

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Change Order No. 2 to the contract with Crossland Heavy Contractors, Inc. for construction of the Black Bob Pump Station Site and Piping Improvements Project, PN 5-RF-001-22.

________________________________________________________________________________

TITLE:

title

Consideration of Change Order No. 2 to the contract with Crossland Heavy Contractors, Inc. for construction of the Black Bob Pump Station Site and Piping Improvements Project, PN 5-RF-001-22.

Body

________________________________________________________________________________

Summary:

This project will modify site piping at the Black Bob Standpipes and Pump Station to allow the larger Black Bob #2 standpipe to be removed from service for maintenance without impacting pump station operations. Continued operation of this pump station is required to maintain adequate pressures in the Southeast Pressure Zone of the distribution system. The original pump station building in the center of the site is no longer in use though still requires continued maintenance each year. This project will demolish the building and convert the area to additional parking lot and green space.

 

During construction, it was discovered that the two large butterfly valves that isolate the Black Bob #2 standpipe from the pump station are in poor operating condition and require replacement. This $61,720 Change Order No. 2 will allow for the replacement of a 24-inch and a 36-inch valve at this site.

 

The original scope of construction has been completed. Work associated with Change Order No. 2 will take place during the fall or winter 2024 season when lower water demands will allow for removing both standpipes and the pump station from service during construction.

________________________________________________________________________________

Financial Impact:

Funding for the Black Bob Pump Station Site and Piping Improvements, as approved in the 2022-2026 Capital Improvement Plan, includes:

 

                     Revenue Bonds                                                                                                                              $675,000

                     Total                                                                                                                                                                        $675,000

________________________________________________________________________________

Action Needed:

Approval of Change Order No. 2 to the contract with Crossland Heavy Contractors, Inc. for construction of the Black Bob Pump Station Site and Piping Improvements Project, PN 5-RF-001-22.

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Project Fact Sheet

C.                     Change Order No. 2