Title: Report on the authorization of the Harold Street, Ridgeview to Kansas City Road, Improvements Project, PN 3-C-074-25.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. CIP Sheet

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Report on the authorization of the Harold Street, Ridgeview to Kansas City Road, Improvements Project, PN 3-C-074-25.

________________________________________________________________________________

TITLE:

title

Report on the authorization of the Harold Street, Ridgeview to Kansas City Road, Improvements Project, PN 3-C-074-25.

Body

________________________________________________________________________________

Summary:

This project is needed to address safety and capacity concerns in the area.  The project will improve Harold Street from the existing collector roadway to a 3-lane arterial section between Ridgeview Road and Kansas City Road.  Improvements will include curb and gutter, storm sewer, streetlights, sidewalks and all other work pertinent to completing the project.

 

The estimated cost for this project is $7,550,000 including design, utility relocations, staff time, land acquisition, permitting, construction and inspection.

 

This project is tentatively scheduled for design in 2025/2026, land acquisition and utility relocations in 2026, and construction in 2027.

________________________________________________________________________________

Financial Impact:

Funding for the Harold Street, Ridgeview to Kansas City Road, Improvements Project, as approved in the 2025-2029 Capital Improvement Plan, includes:                     

                     

GO Bonds                                                                                                         $7,550,000

Total                                                                                                    $7,550,000

 

________________________________________________________________________________

Action Needed:

No action requested at this time.  Staff will return to Council on January 21, 2025, to request approval for authorization of the project.