File #: G25-4819   
Type: Reports Status: Agenda Ready
File created: 12/19/2024 In control: City Council
On agenda: 1/7/2025 Final action:
Title: Report on the authorization of the Lone Elm Road, 119th Street to Harold, Improvements Project, PN 3-C-040-25.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. CIP Sheet

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Report on the authorization of the Lone Elm Road, 119th Street to Harold, Improvements Project, PN 3-C-040-25.

________________________________________________________________________________

TITLE:

title

Report on the authorization of the Lone Elm Road, 119th Street to Harold, Improvements Project, PN 3-C-040-25.

Body

________________________________________________________________________________

Summary:

This project is needed to address safety and capacity concerns in the area.  The project will improve Lone Elm Road from 119th Street to Harold from a 2-lane unimproved roadway to a 2-lane divided arterial section with turn lanes.  Improvements will include pavement construction, curb and gutter, medians, streetlights, sidewalk and sidepath, bike lanes and storm sewers.

 

The estimated cost for this project is $15,860,000 including preliminary and final design, utility relocations, staff time, land acquisition, permitting, construction and inspection.

 

This project is tentatively scheduled for design in 2025/2026, land acquisition and utility relocations in 2026, and construction in 2027.

________________________________________________________________________________

Financial Impact:

Funding for the Lone Elm Road, 119th Street to Harold, Improvements Project, as approved in the 2025-2029 Capital Improvement Plan, includes:                     

                     

GO Bonds                                                                                                         $15,860,000

Total                                                                                                    $15,860,000

 

________________________________________________________________________________

Action Needed:

No action requested at this time.  Staff will return to Council on January 21, 2025, to request approval for authorization of the project.