Title: Consideration of Engineer's Estimate, acceptance of bids and award of contract to Wiedenmann, Inc. for construction of the 151st and Black Bob Waterline Replacement Project, PN 5-C-029-24.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Construction Agreement, 3. C. Engineer's Estimate and Affidavit of Estimate

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Contract with Wiedenmann, Inc. for construction of the 151st and Black Bob Waterline Replacement Project, PN 5-C-029-24.

________________________________________________________________________________

TITLE:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Wiedenmann, Inc. for construction of the 151st and Black Bob Waterline Replacement Project, PN 5-C-029-24.

Body

________________________________________________________________________________

Summary:

This project will abandon the existing waterline within the intersection of 151st Street and Black Bob Road and relocate a new waterline that run outside of the current intersection limits.

 

On March 6, 2025, one (1) bid was received and opened for the above referenced project. Wiedenmann Inc. submitted the responsible bid, in the amount of $274,816.00. The Engineer’s Estimate was $296,750.00. The following is a tabulation of the bids received:

 

                     Wiedenmann, Inc.                                                                                    $274,816.00

                     Engineer’s Estimate                                                                                    $296,750.00

 

Construction is tentatively scheduled to begin August 2025 and be completed in Fall 2025.

________________________________________________________________________________

Financial Impact:

Funding for the 151st and Black Bob Waterline Replacement Project includes:

 

                                          Revenue Bonds                                                                                     $315,000

                                          Total                                                                                                                              $315,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to Wiedenmann, Inc. for construction of the 151st and Black Bob Waterline Replacement Project, PN 5-C-029-24.