Type: Council Consent Status: Passed
File created: 7/29/2025 In control: City Council
On agenda: 8/5/2025 Final action: 8/5/2025
Title: Consideration of Change Order No. 2 with Kaw Roofing and Sheet Metal, Inc. for interior roof drain plumbing and metal deck replacement for the City Hall Environmental Systems Renovation and Roof project PN 6-C-016-19.
Staff Contact: Mary Jaeger, Zach Hardy
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Change Order No. 2

Focus Area: ​Infrastructure (Facilities Management), Facilities

Staff Contact: Mary Jaeger / Zach Hardy

Subject: Change Order No. 2 with Kaw Roofing and Sheet Metal, Inc. for interior roof drain plumbing and metal deck replacement for the City Hall Environmental Systems Renovation and Roof project PN 6-C-016-19. ___________________________________________________________________________

TITLE:

.title

Consideration of Change Order No. 2 with Kaw Roofing and Sheet Metal, Inc. for interior roof drain plumbing and metal deck replacement for the City Hall Environmental Systems Renovation and Roof project PN 6-C-016-19....Body

________________________________________________________________________________

Summary:

The City Hall Environmental Systems Renovation and Roof project is included in the 2019-2024 Capital Improvement Plan with a total project budget of $3,249,400.  This project is for replacement of the HVAC system and building automation controls, and replacement of the roof and roof drainage system. Kaw Roofing and Sheet Metal was awarded the roof replacement portion of the project on December 3, 2024 in the amount of $1,858,950.

 

On May 20, 2025, the City Council approved Resolution No. 25-1047 amending Resolution 22-1046 authorizing $3,249,400 of general obligation bonds for funding of the project and an additional $1,133,238 in insurance funds from prior claim.

 

Change Order No. 2 in the amount of $368,937.50 is for the full replacement of the metal deck underlayment which is substantially rusted during the roof replacement tear off of the roof. The work is required in order to have the new roof adhere to the roof deck and maintain the warranty within the existing contracted work with Kaw Roofing and Sheet Metal.

 

The new contract amount will be $2,257,812.50 and the completion date has extended to August 31, 2025. 

________________________________________________________________________________

Financial Impact:

Funding for the City Hall Environmental Systems Renovation and Roof Replacement Project, includes:

                                          GO Bonds                                                                                                         $3,249,400

                                          Risk Management Fund                                                               $1,133,248

                                          Total                                                                                                                              $4,382,648

________________________________________________________________________________

Action Needed:

Approval of Change Order No. 2 with Kaw Roofing and Sheet Metal, Inc. for interior roof drain plumbing and metal deck replacement for the City Hall Environmental Systems Renovation and Roof project PN 6-C-016-19.

________________________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Change Order No. 2