Title: Consideration of an agreement with Turner Construction for design-build services for the Police Firing Range project, PN 6-C-017-23.
Staff Contact: Mike Butaud, Mary Jaeger, Zach Hardy
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. DBIA Agreement

Focus Area: Police & Infrastructure (Facilities Management)

Staff Contact: Mike Butaud / Mary Jaeger / Zach Hardy

Subject: Contract with Turner Construction for design/build services for the Olathe Police Firing Range project.

________________________________________________________________________________

TITLE:

title

Consideration of an agreement with Turner Construction for design-build services for the Police Firing Range project, PN 6-C-017-23.

Body

________________________________________________________________________________

Summary:

The Olathe Police Firing Range project will design and construct a shooting range complex to serve the training needs of the Olathe Police Department. The project will also include planning, design and construction of all site utilities and site improvements necessary for this project, as well as concept development for a future indoor shooting range facility.

 

On May 20, 2024 staff issued a Request for Qualifications and Cost Proposal for the proposed work to qualified design-build contractors. On June 27, 2024 proposals were received from 7 design-build teams.  The selection committee short-listed 3 teams who were interviewed on August 13, 2024.  The selection committee chose Turner Construction/Treanor Architects from these interviews to award the project.

 

Attached is the proposed agreement with Turner Construction.  This agreement is for design-build services required for the design and construction of the firing range project.  The initial cost for this project is for design and pre-construction services as outlined in the agreement is $516,800.00.

 

The following is the tentative schedule for the design and construction of the project.

 

Design and Master Plan Development:                                                                      Sept 2024-April 2025

Construction:                                                                                                                                                   May 2025-February 2026

Final Completion:                                                                                                                                                                                             March 2026

 

________________________________________________________________________________

Financial Impact:

Funding for the Firing Range Project as proposed in the 2025-2029 Capital Improvement Plan is $13,150,000.00 of General Obligation Bonds and $2,000,000 in federal funds.

________________________________________________________________________________

Action Needed:

Approval of an agreement with Turner Construction for design-build services for the Police Firing Range project, PN 6-C-017-23.