Title: Consideration of Resolution No. 25-1051 authorizing the Police Firing Range Project, PN 6-C-017-23; and amending Resolution No. 23-1066.
Staff Contact: Mike Butaud, Mary Jaeger, Zach Hardy
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Resolution

Focus Area: Police / ​Infrastructure (Facilities Management)

Staff Contact: Mike Butaud / Mary Jaeger / Zach Hardy

Subject: Authorization of the Police Firing Range Project, PN 6-C-017-23.

________________________________________________________________________________

TITLE:

title

Consideration of Resolution No. 25-1051 authorizing the Police Firing Range Project, PN 6-C-017-23; and amending Resolution No. 23-1066.

Body

________________________________________________________________________________

Summary:

The Olathe Police Firing Range project is included in the 2025-2029 Capital Improvement Plan with a total project budget of $15,150,000.  This project is for the design and construction of a shooting range complex to serve the training needs of the Olathe Police Department. The project will also include planning, design and construction of all site utilities and site improvements necessary for this project, as well as concept development for a future indoor shooting range facility.

 

On October 4, 2023, Resolution No. 23-1066 authorized the land acquisition and design phase of the Police Firing Range Project with use of CPR Fund Cash of $2,000,000 and issuance of GO Bonds in an amount not to exceed $2,940,000.

 

On September 17, 2024, a Design/Build Contract was awarded to Turner Construction to begin design. The design is approved, and construction documents are in process to be completed for construction to start in September 2025 with a target completion in August 2026.

 

The Approval of Resolution No. 25-1051 will provide the funding to complete the construction of the Police Firing Range Project, PN 6-C-017-23.

________________________________________________________________________________

Financial Impact:

Funding of the Police Firing Range includes:

 

FBI Grant                                                               $  2,000,000

General Obligation Bonds                     $13,150,000

                                                                                    TOTAL                     $15,150,000

________________________________________________________________________________

Action Needed:

Approval of Resolution No. 25-1051 authorizing the Police Firing Range Project, PN 6-C-017-23; and amending Resolution No. 23-1066.

________________________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Resolution