File #: G25-4828   
Type: Reports Status: Agenda Ready
File created: 12/19/2024 In control: City Council
On agenda: 1/7/2025 Final action:
Title: Report on the authorization of the Salt Barn #2 Project, PN 6-C-030-25.
Staff Contact: Mary Jaeger, Zach Hardy
Attachments: 1. A. CIP Sheet

Focus Area: Infrastructure (Field Operations)

Staff Contact: Mary Jaeger / Zach Hardy

Subject: Report on the authorization of the Salt Barn #2 Project, PN 6-C-030-25.

________________________________________________________________________________

TITLE:

title

Report on the authorization of the Salt Barn #2 Project, PN 6-C-030-25.

Body

________________________________________________________________________________

Summary:

This project includes the design and construction of an 80’ x 140’ fabric and steel framed building set on a concrete pad and pier foundations. The building will serve as a second City of Olathe Salt Barn capable of holding 6,000 tons of salt for the City’s Snow and Ice Operations. The new building will allow the city to discontinue leasing space in the Meritex caves saving $18K per year.

 

Location for the building, including the Robinson campus, are currently being evaluated and assessed.

 

The estimated cost for this project is $655,000 including design, land assessment, permitting, construction and inspection.

 

Design and construction of the new salt barn is tentatively scheduled for 2025/2026.

________________________________________________________________________________

Financial Impact:

Funding for the Salt Barn #2 Project, as approved in the 2025-2029 Capital Improvement Plan, includes:                     

                     

GO Bonds                                                                                                         $655,000

Total                                                                                                    $655,000

________________________________________________________________________________

Action Needed:

No action requested at this time.  Staff will return to Council on January 21, 2025, to request approval for authorization of the project.

________________________________________________________________________________

Attachment(s):

A. CIP Sheet