City of Olathe header
File #: G25-4889   
Type: Council Consent Status: Agenda Ready
File created: 1/21/2025 In control: City Council
On agenda: 2/4/2025 Final action:
Title: Consideration of Engineer's Estimate, acceptance of bids and award of contract to Sands Construction, LLC for construction of the Prairie Center Park Improvements Phase 1 Project, PN 4-C-016-22.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Construction Agreement, 4. D. Engineer's Estimate and Affidavit of Cost

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Sands Construction, LLC for construction of the Prairie Center Park Improvements Phase 1 project, PN 4-C-016-22.

________________________________________________________________________________

title:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Sands Construction, LLC for construction of the Prairie Center Park Improvements Phase 1 Project, PN 4-C-016-22.

Body

________________________________________________________________________________

Summary:

This project will provide a new parking lot for visitors and baseball patrons, two new pickleball courts, sidewalks, and drainage improvements on the north side of the park. On the south side of the park, patrons will see new concrete concourses at the baseball fields and new baseball backstops (separate agreement).

 

On December 6, 2024, six (6) bids were received and opened for the above referenced project. Sands Construction, LLC was the responsible bidder in the amount of $1,398,353.00. The Engineer’s Estimate was submitted at $1,721,938.16. The following is a tabulation of the bids received:

 

Sands Construction                                                                                    $ 1,398,353.00

R&R Concrete                                                                                    $ 1,440,209.08

McAnany Construction                                                               $ 1,584,300.00

McConnell & Associates                                                               $ 1,610,025.75

MegaKC Corp.                                                                                    $ 1,710,744.00

Engineer’s Estimate                                                                                    $ 1,721,938.16

Kansas Heavy Construction                                          $ 1,782,003.35

 

Construction is tentatively scheduled to begin in February 2025 and completed in Fall/Winter 2025.

________________________________________________________________________________

Financial Impact:

Funding for the Prairie Center Park Improvements Project includes:

 

                                          Park Sales Tax Fund                                                               $2,183,000

Total                                                                                                    $2,183,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to Sands Construction, LLC for construction of the Prairie Center Park Improvements Phase 1 Project, PN 4-C-016-22.

________________________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Construction Agreement

D. Engineer’s Estimate and Affidavit of Cost