Title: Consideration of Resolution No. 25-1015 authorizing the Black Bob Road, 153rd Terrace to 159th Street, Improvements Project, PN 3-C-041-23; and amending Resolution 23-1022.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Resolution

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Authorization of the Black Bob Road, 153rd Terrace to 159th Street, Improvements Project, PN 3-C-041-23.

________________________________________________________________________________

TITLE:

title

Consideration of Resolution No. 25-1015 authorizing the Black Bob Road, 153rd Terrace to 159th Street, Improvements Project, PN 3-C-041-23; and amending Resolution 23-1022.

Body

________________________________________________________________________________

Summary:

This project will improve Black Bob Road from 153rd Terrace to 159th Street from a 2-lane roadway to a 4-lane divided arterial section.  Improvements will include pavement construction, bike lanes, curb and gutter, medians, streetlights, sidewalk and side path and storm sewers.

 

On March 21, 2023, Council authorized the Black Bob Road, 153rd Terrace to 159th Street, Improvements Project in the amount of $13,595,700.  In the 2025-2029 CIP, the project amount was increased to $17,595,700 due to inflationary costs of the estimated bridge construction and the addition of arterial section improvements to 159th Street, east and west of the intersection with Black Bob Road.  At the time, it was anticipated that the City would receive $4,000,000 in CARS funding for the project; however, the City was only awarded $3,755,000 in CARS funding for the project.  This Resolution will increase the overall project amount by the $3,755,000, the amount of CARS funding awarded to the project.  There is no increase in the GO Bond amount for the project.

 

Construction of this project is tentatively scheduled to begin in Fall 2025.  

________________________________________________________________________________

Financial Impact:

Funding for the Black Bob Road, 153rd Terrace to 159th Street, Improvements Project includes:

 

CARS                                                                                                                              $  3,755,000

GO Bonds                                                                                                         $13,595,700

Total                                                                                                                              $17,350,700                       

 

________________________________________________________________________________

Action Needed:

Approval of Resolution No. 25-1015 authorizing the Black Bob Road, 153rd Terrace to 159th Street, Improvements Project, PN 3-C-041-23; and amending Resolution 22-1022.

________________________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Resolution