Type: Council Consent Status: Agenda Ready
File created: 5/8/2025 In control: City Council
On agenda: 5/20/2025 Final action:
Title: Consideration of Interlocal Agreement with Johnson County Wastewater for reimbursement of work associated with the JCW Doghouse Manhole Project, 1-C-023-22.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Interlocal Agreement

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Reimbursement Agreement with Johnson County Wastewater for work associated with the JCW Doghouse Manhole Project, PN 1-C-023-22.

________________________________________________________________________________

TITLE:

title

Consideration of Interlocal Agreement with Johnson County Wastewater for reimbursement of work associated with the JCW Doghouse Manhole Project, 1-C-023-22.

 

Body

________________________________________________________________________________

Summary:

This project will replace Johnson County Wastewater (JCW) corroded 24-inch ductile iron sanitary sewer main that crosses directly through Olathe’s 48-inch Indian Creek sanitary sewer interceptor manhole. Olathe constructed the manhole around JCW’s existing 24-inch sanitary sewer main due to both mains having the exact same elevations and topography. Following the replacement, the manhole and the crossing pipe will be epoxy lined to extend the life of the City’s manhole and the JCW sanitary sewer main.  During construction it was determined by JCW and our contractor the best solution would be to thermoliner their sanitary sewer main and not replace just the section through the manhole.

 

This agreement will allow JCW to reimburse the City for thermolining that was performed on their sewer main that intersects one of our manhole structures in the Indian Creek sewer basin.

 

The construction cost for the thermoliner is $67,361.  This cost includes the cost of the material and installation of the liner.

 

Construction of the City’s project was completed in late Fall 2024.

________________________________________________________________________________

Financial Impact:

Funding for the JCW Doghouse Manhole Project includes:

 

Water/Sewer Fund                        $475,200

________________________________________________________________________________

Action Needed:

Approval of Interlocal Agreement with Johnson County Wastewater for the JCW Doghouse Manhole Project, PN 1-C-023-22.

________________________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Interlocal Agreement