Legislation Details

File #: G26-5692   
Type: Council Consent Status: Passed
File created: 4/8/2026 In control: City Council
On agenda: 4/21/2026 Final action: 4/21/2026
Title: Consideration of Engineer's Estimate, acceptance of bids, and award of contract to SAK Construction, LLC for construction of the Arrowhead Truss Mains Sanitary Sewer Rehabilitation Project, PN 1-R-003-23.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Construction Agreement, 4. D. Engineer's Estimate and Affidavit of Estimate

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Contract with SAK Construction, LLC for construction of the Arrowhead Truss Mains Sanitary Sewer Rehabilitation Project, PN 1-R-003-23.

________________________________________________________________________________

TITLE:

title

Consideration of Engineer’s Estimate, acceptance of bids, and award of contract to SAK Construction, LLC for construction of the Arrowhead Truss Mains Sanitary Sewer Rehabilitation Project, PN 1-R-003-23.

Body

________________________________________________________________________________

Summary:

This project will include the lining of approximately 7,500 linear feet of sanitary sewer pipes that have reached the end of their useful life. These improvements will reduce the risk of sanitary sewer overflows and sewer backups into residents’ homes and reduce the Johnson County Wastewater bill by reducing the flow of inflow and infiltration (I&I) into the Indian Creek basin.

 

On March 26, 2026 five (5) bids were received and opened for the above referenced project.  The bids ranged from $692,810.00 to $1,543,140.00 with the Engineer’s Estimate at $1,066,000.00. SAK Construction, LLC submitted the low and responsible bid in the amount of $692,810.00. The following is a tabulation of the bids received:

 

SAK Construction, LLC                                                               $   692,810.00

Havens Construction Company, Inc.                     $   708,840.00

Insituform Technologies USA, LLC                     $   785,483.04

Municipal Pipe Tool                                                                                    $   894,947.50

                     Engineer’s Estimate                                                                                    $1,066,000.00

                     Ace Pipe Cleaning Inc                                                               $1,543,140.00

 

Construction is tentatively scheduled to begin in May 2026 and tentatively scheduled to be completed in August 2026.

________________________________________________________________________________

Financial Impact:

Funding for the Arrowhead Truss Mains Sanitary Sewer Rehabilitation Project includes:

 

Revenue Bonds                                                                                                                              $697,810

                     Total                                                                                                                                                                        $697,810

 

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to SAK Construction, LLC for construction of the Arrowhead Truss Mains Sanitary Sewer Rehabilitation Project, 1-R-003-23.

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Project Fact Sheet

C.                     Construction Agreement

D.                     Engineer’s Estimate and Affidavit of Estimate