File #: G25-5330   
Type: Council Consent Status: Passed
File created: 9/22/2025 In control: City Council
On agenda: 10/7/2025 Final action: 10/7/2025
Title: Consideration of Resolution No. 25-1087 authorizing the 159th Street, Brougham to Black Bob, Improvements Project, PN 3-C-003-25; and amending Resolution 25-1005.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Resolution

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Authorization of the 159th Street, Brougham to Black Bob, Improvements Project, PN 3-C-003-25; and amending Resolution 25-1005.

________________________________________________________________________________

TITLE:

title

Consideration of Resolution No. 25-1087 authorizing the 159th Street, Brougham to Black Bob, Improvements Project, PN 3-C-003-25; and amending Resolution 25-1005.

Body

________________________________________________________________________________

Summary:

This project will improve 159th Street from Brougham Drive to Black Bob Road from a 2-lane rural section to an improved 2-lane arterial with turn lanes. Improvements will include pavement construction, curb and gutter, streetlights, sidewalks, storm sewer, modifications to the existing stream crossing and a new traffic signal at 159th and Brougham.

 

On January 21, 2025, City Council approved Resolution 25-1005 authorizing a project to improve 159th Street from Mur-Len to Black Bob to a 4-lane divided arterial section with turn lanes.  During the 2026 budget process, the scope of this project was modified to reduce the overall cost of the project from $20,365,000 to $10,775,000.  This resolution establishes the updated scope and cost of the project.

 

The estimated cost for this project is $10,775,000 including preliminary and final design, utility relocations, staff time, land acquisition, permitting, construction and inspection.

 

This project is tentatively scheduled for design in 2025/2026, land acquisition and utility relocations in 2026, and construction in 2027.

________________________________________________________________________________

Financial Impact:

Funding for the 159th Street, Brougham to Black Bob, Improvements Project, as approved in the 2026-2030 Capital Improvement Plan, includes:

 

                                          GO Bonds                                                                                                         $10,775,000

                                          Total                                                                                                                              $10,775,000

________________________________________________________________________________

Action Needed:

Approval of Resolution No. 25-1087 authorizing the 159th Street, Brougham to Black Bob, Improvements Project, PN 3-C-003-25; and amending Resolution 25-1005.