File #: G24-4466   
Type: Council Consent Status: Passed
File created: 6/5/2024 In control: City Council
On agenda: 6/18/2024 Final action: 6/18/2024
Title: Consideration of an Agreement with Johnson County for construction of the Indian Creek - Lindenwood, Jamestown to Arrowhead, Stormwater Improvement Project, PN 2-C-016-22
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Agreement

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Agreement with Johnson County for construction of the Indian Creek - Lindenwood, Jamestown to Arrowhead, Stormwater Improvement Project, PN 2-C-016-22.

________________________________________________________________________________

TITLE:

title

Consideration of an Agreement with Johnson County for construction of the Indian Creek - Lindenwood, Jamestown to Arrowhead, Stormwater Improvement Project, PN 2-C-016-22..

 

Body

________________________________________________________________________________

Summary:

This project will address street and structure flooding caused by Indian Creek along Lindenwood Drive, in the vicinity of Jamestown Drive to Arrowhead Drive. Flooding at Pawnee Drive, which currently serves as an access point to Heritage Elementary School, is within the project area and will also be addressed.

 

The project will include culvert replacement with a bridge, channel improvements, storm sewer improvements, and street reconstruction with raised elevations.  The project will reduce the risk of flooding for five (5) homes identified within the 100-year FEMA floodplain and minimize overtopping of Lindenwood Drive, Pawnee Drive, Mohawk Drive, Cherokee Lane, Jamestown Drive and three cul-de-sacs along Lindenwood Drive.  No home buyouts are included with this project.

 

This project was chosen to be funded by Johnson County’s Stormwater Management Advisory Council (SMAC) program in the amount of $2,307,500 (50% of a maximum $4,615,000) for the design and construction of the project.  On April 2, 2024, the City approved a construction agreement with Pyramid Contractors, Inc., for construction of this project.  In order for the City to accept County funding for construction, the City must approve this construction agreement with the Johnson County SMAC program. The County has agreed to include additional funds in the construction agreement, raising reimbursable levels to $2,538,250 (50% of a maximum $5,076,500), as construction costs have increased since the project was funded.

 

Construction of this project started in May 2024, with construction completion anticipated for Spring 2025.

________________________________________________________________________________

Financial Impact:

Funding for the Indian Creek - Lindenwood, Jamestown to Arrowhead, Stormwater Improvement Project, as approved in the 2024-2028 Capital Improvement Plan, includes:

 

                     Revenue Bonds                                                                                    $3,470,000

Olathe Stormwater Fund                                                               $1,172,500

Johnson County SMAC Program                                          $2,307,500

                     Total                                                                                                                              $6,950,000

________________________________________________________________________________

Action Needed:

Approval of an Agreement with Johnson County for construction of the Indian Creek - Lindenwood, Jamestown to Arrowhead, Stormwater Improvement Project, PN 2-C-016-22.

________________________________________________________________________________