Focus Area: Infrastructure (Engineering)
Staff Contact: Mary Jaeger / Nate Baldwin
Subject: Report on the authorization of the Lone Elm, 159th Street to 167th Street, Improvements Project, PN 3-C-076-25.
________________________________________________________________________________
TITLE:
title
Report on the authorization of the Lone Elm, 159th Street to 167th Street, Improvements Project, PN 3-C-076-25.
Body
________________________________________________________________________________
Summary:
This project is needed to address safety and capacity concerns in the area. The project will improve Lone Elm Road from 159th Street to 167th Street from the existing 2-lane section to a 4-lane divided arterial. Improvements will include pavement construction curb and gutter, medians, streetlights, sidewalks, turn lanes, and storm sewers.
The estimated cost for this project is $16,273,000 including preliminary and final design, utility relocations, staff time, land acquisition, permitting, construction and inspection.
This project is tentatively scheduled for design in 2025/2026, land acquisition and utility relocations in 2026, and construction in 2027.
________________________________________________________________________________
Financial Impact:
Funding for the Lone Elm, 159th Street to 167th Street, Improvements Project, as approved in the 2025-2029 Capital Improvement Plan, includes:
GO Bonds $16,273,000
Total $16,273,000
________________________________________________________________________________
Action Needed:
No action requested at this time. Staff will return to Council on January 21, 2025, to request approval for authorization of the project.
________________________________________________________________________________
Attachment(s):
A. Project Location Map
B. Project Fact Sheet
C. CIP Sheet