Focus Area: Infrastructure
Staff Contact: Mary Jaeger / Nate Baldwin
Subject: Agreement with Johnson County for funding the construction of the CMP Replacement: 143rd Street and Lakeshore Drive Arterial Mill and Overlay Projects, PN 2-R-001-25.
________________________________________________________________________________
TITLE:
title
Consideration of an Agreement with Johnson County for funding the construction of the CMP Replacement: 143rd Street and Lakeshore Drive Arterial Mill and Overlay Projects, PN 2-R-001-25.
Body
________________________________________________________________________________
Summary:
This Agreement will reimburse 50% of the construction costs associated with improving deficient stormwater assets along 143rd Street (Mur-Len to Black Bob), and Lakeshore Drive (Dennis to Santa Fe). During the mill and overlay projects, seventeen failing CMP stormwater pipes will be replaced with new reinforced concrete stormwater pipes.
This project was chosen to be funded by Johnson County’s Stormwater Management Advisory Council (SMAC) in the amount of $274,750 (50% of $549,500). In order to accept this funding, the City must approve this Agreement with Johnson County.
Construction is scheduled to begin in Summer 2025.
________________________________________________________________________________
Financial Impact:
Approval of this agreement will result in $274,750 of funding from Johnson County SMAC for the CMP Replacement: 143rd Street and Lakeshore Drive Arterial Mill and Overlay Projects, PN 2-R-001-25.
________________________________________________________________________________
Action Needed:
Approval of an Agreement with Johnson County for construction of the CMP Replacement: 143rd Street and Lakeshore Drive Arterial Mill and Overlay Projects, PN 2-R-001-25.
________________________________________________________________________________
Attachment(s):
A. Project Location Map
B. Agreement