City of Olathe header
To visit archives prior to April 2024 please click here.
File #: G19-505   
Type: New Business-Public Works Status: Agenda Ready
File created: 1/7/2019 In control: City Council
On agenda: 1/22/2019 Final action: 1/22/2019
Title: Consideration of an Agreement with Finkle Williams, Inc. for design of the Fire Station #8 Improvements Project, PN 6-C-009-18. .
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. Attachment A Agreement, 2. Attachment B Project Fact Sheet, 3. Attachment C Project Location Map

Department: Public Works

Staff Contact: Mary Jaeger/Beth Wright

Subject: This agreement will provide for design services for Fire Station #8.

________________________________________________________________________________

Item Description:

title

Consideration of an Agreement with Finkle Williams, Inc. for design of the Fire Station #8 Improvements Project, PN 6-C-009-18. .

Body

________________________________________________________________________________

Summary:

Improved Fire Department coverage is needed to better serve the growing southwestern portion of the community, including increasing residential density, Mission Trail Middle School and the I-35 Logistics Park.  This project is for the planning, design, construction, and equipping of a new fire station.  In coordination with the Parks & Recreation department, this will be the initial phase of development of the approximately 12 acres of property recently purchased at 148th Street & Lakeshore Drive.

Design and construction of the Fire Station #8 project will utilize the Construction Manager At-Risk contract method.  On October 18, 2018, staff issued a Request for Qualifications (RFQ) to firms seeking to be considered for providing design services for this project as well the Fire Training Center Improvements Project. On October 30, 2018, Statements of Qualifications were received from eight (8) design teams. The evaluation and selection committee identified three (3) teams to be interviewed and provide fee proposals. Following the interviews on December 11, 2018, the committee identified Finkle Williams, Inc. as the preferred firm for this project.

Attached is the proposed Agreement with Finkle Williams, Inc.  The Agreement is for comprehensive planning, design, and construction administration services.  The total cost of services as outlined in the Agreement is $363,400.

The following is the tentative schedule for the design and construction of the project:

Begin Planning and Design:                     January 2019

Complete Design:                     September 2019

Bidding                                          October 2019                     

Begin Construction:                     November 2019

Complete Construction:                     February 2021

________________________________________________________________________________

Financial Impact:

Funding for the Fire Station #8 Improvements Project, as approved in the 2019 Capital Improvement Plan, includes:

GO Bonds                                                                                                         $7,055,000

Total                                                                                                                              $7,055,000

 

________________________________________________________________________________

Action Needed:

Approval of an Agreement with Finkle Williams, Inc. for design of the Fire Station #8 Improvements Project, PN 6-C-009-18.

________________________________________________________________________________

Attachment(s):

A: Agreement

B: Project Fact Sheet

C: Project Location Map