File #: G19-540   
Type: Council Consent Status: Passed
File created: 1/22/2019 In control: City Council
On agenda: 2/5/2019 Final action: 2/5/2019
Title: Consideration of Engineer’s Estimate, acceptance of bids and award of contract to O’Donnell & Sons Construction Co., Inc. for construction of the 151st Street Arterial Mill and Overlay Project, PN 3-P-004-19.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A Engineer's Estimate and Affidavit of Estimate, 2. B Project Location Map, 3. C Resolution 19-1007

Department: Public Works

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with O’Donnell & Sons Construction Co., Inc. for construction of the 151st Street Arterial Mill and Overlay Project, PN 3-P-004-19.

________________________________________________________________________________

Item Description:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to O’Donnell & Sons Construction Co., Inc. for construction of the 151st Street Arterial Mill and Overlay Project, PN 3-P-004-19..

________________________________________________________________________________

Summary:

On January 23, 2019, four (4) bids were received and opened for the above referenced project.  The bids ranged from $747,813.85 to $834,848.20 with the Engineer’s Estimate at $914,326.50. O’Donnell & Sons Construction Co., Inc. submitted the low and responsible bid in the amount of $747,813.35. The following is a tabulation of the bids received:

 

O’Donnell & Sons Construction Co., Inc.                                          $ 747,813.85

McAnany Construction, Inc.                                                               $ 761,369.84

Bettis Asphalt                                                                                                         $ 818,219.94

J.M. Fahey Construction Company                                          $ 834,848.20

Engineer’s Estimate                                                                                                         $ 914,326.50

 

This Street Preservation project, from Pflumm Road to Quivira Road, will include a two-inch asphalt mill and overlay, asphalt base repair, concrete curb and gutter replacement, sidewalk and ADA ramp replacement, pavement markings, pedestrian signal installation, and traffic detection maintenance. The City of Olathe and the City of Overland Park will share the costs of design and construction. The City of Olathe will administer the project.

 

Construction is scheduled to begin in late Spring 2019 and will be completed in Summer 2019.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2019 Street Preservation Program authorized on January 22, 2019. The City of Overland Park’s share will be 18.5% of the total cost, estimated to be $176,535.14. Authorized revenue for the 2019 Street Preservation Program includes:                     

 

Street Maintenance Sales Tax                                          $12,750,000

CIP Fund                                                                                                          $  2,800,000

General Obligation Bonds                                                               $  1,000,000

Total                                                                                                              $16,550,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to O’Donnell & Sons Construction Co., Inc. for construction of the 151st Street Arterial Mill and Overlay Project, PN 3-P-004-19.

________________________________________________________________________________

Attachment(s):

A:  Engineer’s Estimate and Affidavit of Estimate

B:  Project Location Map

C:  Resolution 19-1007