File #: G19-646   
Type: Council Consent Status: Agenda Ready
File created: 3/6/2019 In control: City Council
On agenda: 3/19/2019 Final action:
Title: Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Freeman Concrete Construction, LLC for construction of the Wabash Street Improvements Project, PN 3-R-003-19.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A: Engineers Estimate and Affidvit of Estimate, 2. B: Project Location Map, 3. C: Resolution 18-1078

Department: Public Works

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with Freeman Concrete Construction, LLC for construction of the Wabash Street Improvements Project, PN 3-R-003-19.

________________________________________________________________________________

Item Description:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Freeman Concrete Construction, LLC for construction of the Wabash Street Improvements Project, PN 3-R-003-19..

________________________________________________________________________________

Summary:

On March 6, 2019, five (5) bids were received and opened for the above referenced project.  The bids ranged from $ 468,860.70 to $ 604,382.00 with the Engineer’s Estimate at $ 588,088.00. Freeman Concrete Construction, LLC submitted the low and responsible bid in the amount of $ 468,860.70. The following is a tabulation of the bids received:

 

Freeman Concrete Construction, LLC                                          $ 468,860.70

Linaweaver Construction, Inc.                                                               $ 535,786.00

Amino Brothers Co., Inc.                                                                                    $ 552,608.45

Gunter Construction Company                                                               $ 562,279.00

Engineer’s Estimate                                                                                                         $ 588,088.00

O’Donnell & Sons Construction Co., Inc.                      $ 604,382.00

 

This Street Reconstruction project will include replacement of the existing pavement section, concrete curb and gutter, ADA sidewalk ramps, sidewalk, city street light installation, stormwater improvements and pavement markings on Wabash Street between Parker Street and Troost Street (see attached Project Location Map).

 

Construction is scheduled to begin in Spring 2019 and will be completed in Fall 2019.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2019 Street Reconstruction Program authorized on September 4, 2019. Authorized revenue for the 2019 Street Reconstruction Program includes:                     

 

General Obligation Bonds                                                               $  5,100,000

Total                                                                                                              $  5,100,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to Freeman Concrete Construction, LLC for construction of the Wabash Street Improvements Project, PN 3-R-003-19.

________________________________________________________________________________

Attachment(s):

A:  Engineer’s Estimate and Affidavit of Estimate

B:  Project Location Map

C:  Resolution 18-1078