Title: Consideration of a Relocation and Reimbursement Agreement with ATMOS Energy Corporation for the Lone Elm Road, Old 56 Hwy to 151st, Improvements Project, PN 3-C-084-17
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A: Relocation and Reimbursement Agreement, 2. B: Project Fact Sheet, 3. C: Project Location Map

epartment: Public Works

Staff Contact: Mary Jaeger / Beth Wright

Subject: An agreement with ATMOS for utility relocations for the Lone Elm Road, Old 56 Hwy to 151st, Improvements Project, PN 3-C-084-17.

________________________________________________________________________________

Item Description:

title

Consideration of a Relocation and Reimbursement Agreement with ATMOS Energy Corporation for the Lone Elm Road, Old 56 Hwy to 151st, Improvements Project, PN 3-C-084-17..

Body

________________________________________________________________________________

Summary:

This agreement is in place to relocate the necessary portions of the ATMOS utility lines located along Lone Elm Road between Old 56 Highway and 151st Street.  This relocation is necessary to move the utility to a location that will allow for the City of Olathe to construction the improvements associated with the Lone Elm Road, Old 56 Hwy to 151st, Improvements Project.  

 

ATMOS has provided an estimated total cost of $130,161 for the relocation work.  Olathe’s portion of the estimated cost is $76,014. This estimate reflects 58.4% of the total cost of relocation of the utility equipment located within existing utility easements along the corridor.  These costs include all materials, construction, labor, survey, inspection, and other costs necessary to complete the relocations in the area. 

 

The relocation of these lines is tentatively scheduled to begin in this month with completion by the end of 2019.

_______________________________________________________________________________

Financial Impact:

Funding for the Lone Elm Road, Old 56 Hwy to 151st, Improvements Project, as approved in the 2019 Capital Improvement Plan, includes: 

                     

                                          GO Bonds                                                                                          $13,675,000

                                          CARS                                                                                                         $  2,000,000

                                          STP                                                                                                         $  3,785,000

                                          Total                                                                                                         $19,460,000

________________________________________________________________________________

Action Needed:

Approval of a Relocation and Reimbursement Agreement with ATMOS Energy Corporation for the Lone Elm Road, Old 56 Hwy to 151st, Improvements Project, PN 3-C-084-17.

________________________________________________________________________________

Attachment(s):

A:  Relocation and Reimbursement Agreement

B:  Project Fact Sheet

C:  Project Location Map