File #: G20-1366   
Type: Council Consent Status: Agenda Ready
File created: 1/9/2020 In control: City Council
On agenda: 1/21/2020 Final action:
Title: Consideration of a Professional Services Agreement with HNTB Corporation for design of the Downtown Streets Improvements Project, PN 3-R-001-21
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A: Professional Services Agreement, 2. B: Project Location Map

Department: Public Works

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with HNTB Corporation for design of the Downtown Streets Improvements Project, PN 3-R-001-21.

________________________________________________________________________________

Item Description:

title

Consideration of a Professional Services Agreement with HNTB Corporation for design of the Downtown Streets Improvements Project, PN 3-R-001-21..

Body

________________________________________________________________________________

Summary:

On November 25, 2019, the City advertised a Request for Qualifications (RFQ) for engineering companies to provide design services to improve four downtown streets. Five (5) firms responded to the RFQ.  After reviewing all proposals, the selection committee chose HNTB Corporation as the most qualified firm.

 

The $339,990 Professional Services Agreement provides engineering services necessary for design of the reconstruction project, including survey of existing conditions, utility coordination, public involvement, acquisition documentation (title reports, surveyed exhibits, easement documents, etc.) needed for any right-of-way or easements, development of construction plans in accordance with Olathe design standards and specifications, cost estimates, assistance with bidding of project for construction, and assistance as needed throughout construction.

 

Improvements on the four downtown streets will include full depth asphalt pavement and subgrade replacement, replacement of concrete curb and gutters, replacement of sidewalk, installation of missing segments of sidewalk, driveway approaches, street light installation, stormwater improvements, and sanitary sewer improvements.

 

It is anticipated that design will begin immediately following approval of this agreement.  Staff anticipates bringing a construction contract for the first phase of improvements to the City Council for consideration in Summer 2020.  Improvements for all phases are expected to be completed by the end of 2021.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2021 Street Reconstruction Program authorized on January 21, 2020. Authorized revenue for the 2021 Street Reconstruction Program includes:                     

 

General Obligation Bonds                                                                                    $ 5,100,000

Total                                                                                                                                                   $ 5,100,000

________________________________________________________________________________

Action Needed:

Approval of a Professional Services Agreement with HNTB Corporation for design of the Downtown Streets Improvements Project, PN 3-R-001-21.