Type: Council Consent Status: Agenda Ready
File created: 1/21/2020 In control: City Council
On agenda: 2/4/2020 Final action:
Title: Consideration of Resolution No. 20-1016 authorizing funding for Pflumm Road, 143rd to 151st, Improvements Project, PN 3-C-114-20.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Resolution, 2. B. Project Fact Sheet, 3. C. Project Location Map

Department: Public Works

Staff Contact: Mary Jaeger / Beth Wright

Subject: Authorization of the Pflumm Road, 143rd to 151st, Improvements Project, PN 3-C-114-20.

________________________________________________________________________________

Item Description:

title

Consideration of Resolution No. 20-1016 authorizing funding for Pflumm Road, 143rd to 151st, Improvements Project, PN 3-C-114-20.

________________________________________________________________________________

Summary:

This project is needed to address capacity and safety concerns in the area.

 

This project will improve Pflumm Road to a four-lane divided arterial roadway between 143rd Street and 151st Street.  Also included will be geometric improvements at both intersections and a new traffic signal at 151st & Pflumm. Improvements will include storm sewer, medians, curb and gutter, new streetlights, on-street bike lanes, sidewalks and all other work necessary to complete the project. 

 

The estimated cost for this project is $18,715,000.  This includes preliminary and final design, utility relocation, survey, staff time, construction, construction inspection and land acquisition.

 

This project is tentatively scheduled for design in 2020, land acquisition in 2020/2021, utility relocations in 2021 and construction in 2022.

 

________________________________________________________________________________

Financial Impact:

Funding for the Pflumm Road, 143rd to 151st, Improvements Project includes:

                     

                                          CARS                                                                                                                              $  2,000,000

                                          Federal (STP)                                                                                    $  1,500,000                                                               

GO Bonds                                                                                                         $15,215,000

Total                                                                                                    $18,715,000

________________________________________________________________________________

Action Needed:

Approval of Resolution No. 20-1016 authorizing funding for Pflumm Road, 143rd to 151st, Improvements Project, PN 3-C-114-20.

______________________________________________________________________                     