City of Olathe header
To visit archives prior to April 2024 please click here.
File #: G20-1639   
Type: Council Consent Status: Agenda Ready
File created: 5/4/2020 In control: City Council
On agenda: 5/19/2020 Final action:
Title: Consideration of an Agreement with ATMOS Energy Corporation for the Upper Cedar Creek, 169 Hwy to Mahaffie, Stormwater Improvements Project, PN 2-C-013-19.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Agreement

Department: Public Works

Staff Contact: Mary Jaeger / Beth Wright

Subject: An agreement with ATMOS Energy Corporation for utility relocations for the Upper Cedar Creek, 169 Hwy to Mahaffie, Stormwater Improvements Project, PN 2-C-013-19.

________________________________________________________________________________

Item Description:

title

Consideration of an Agreement with ATMOS Energy Corporation for the Upper Cedar Creek, 169 Hwy to Mahaffie, Stormwater Improvements Project, PN 2-C-013-19..

________________________________________________________________________________

Summary:

This project is in place to address street and structure flooding that occurs in the vicinity of the intersection of S. Keeler Street and S. Keeler Terrace.  The project includes replacement of existing corrugated metal pipe (CMP) culverts with larger concrete culverts, reconstruction of street pavement, channel improvements, storm sewer improvements, and the elimination of the flood risk for two (2) businesses identified within the 100-year floodplain through project improvements. 

 

This is the second of six identified neighborhood flood control projects located outside the FEMA regulated floodplain.

 

This agreement would allow ATMOS Energy Corporation (ATMOS)to relocate necessary portions of their infrastructure that are in conflict with the City’s proposed stormwater improvements along S. Keeler Street and S. Keeler Terrace.

 

ATMOS’s infrastructure is within a private easement, therefore the City must reimburse ATMOS for all costs associated with the relocation effort.  ATMOS estimates the cost to be $99,096.00.  The actual costs will be reconciled when ATMOS completes their relocation work.

 

The relocation of the ATMOS facilities is tentatively scheduled to begin in Summer 2020 with completion by the end of 2020.

 

Construction of the project is tentatively scheduled to begin in Spring 2021.

 

___________________________________________________________________________

Financial Impact:

Funding for the Upper Cedar Creek, 169 Hwy to Mahaffie, Stormwater Improvements Project, as approved in the 2019 Capital Improvement Plan, includes: 

 

                     Olathe Stormwater Fund                                                               $1,184,430

Johnson County SMAC Program                                          $1,350,570

                     Total                                                                                                                              $2,535,000

________________________________________________________________________________

Action Needed:

Approval of an Agreement with ATMOS Energy Corporation for the Upper Cedar Creek, 169 Hwy to Mahaffie, Stormwater Improvements Project, PN 2-C-013-19.

______________________________________________________________________                     

Attachment(s):

A.  Project Location Map                     

B.  Project Fact Sheet

C.  Agreement