Title: Consideration of Architect's Estimate, acceptance of bids, and award of contract to Crossland Construction, Inc. for construction of the Fire Training Center Improvements Project, PN 6-C-004-13
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Architect's Estimate and Affidavit of Estimate, 4. D. Agreement

Department: Public Works

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with Crossland Construction, Inc. for construction of the Fire Training Center Improvements Project, PN 6-C-004-13.

________________________________________________________________________________

Item Description:

title

Consideration of Architect’s Estimate, acceptance of bids, and award of contract to Crossland Construction, Inc. for construction of the Fire Training Center Improvements Project, PN 6-C-004-13..

Body

________________________________________________________________________________

Summary:

On May 14, 2020, eleven (11) bids were received and opened for the above referenced project.  The bids ranged from $1,941,900 to $2,469,800 with the Architect’s Estimate at $2,775,111.  Crossland Construction, Inc. submitted the low and responsible bid in the amount of $1,941,900, inclusive of two required allowances and three alternates.  The following is a summary of the bids received:

 

                                          Base Bid                     Allowances (2)                     Alternates (3)                     Total

                     Crossland Construction                     $1,772,000                     $63,500                     $106,400                     $1,941,900

                     Haren Companies                     $1,835,817                     $60,100                     $85,116                     $1,981,033

                     Excel Constructors                     $1,848,000                     $100,000                     $104,100                     $2,052,100

                     Trinium                     $1,875,000                     $90,000                     $89,000                     $2,054,000

                     B. Dean Construction                     $1,905,400                     $70,600                     $111,200                     $2,087,200

                     Combes Construction                     $2,012,000                     $49,500                     $100,000                     $2,161,500

                     Rothwell Construction                     $2,038,445                     $66,500                     $99,411                     $2,204,356

                     Infinity Group                     $2,179,478                     $70,000                     $79,503                     $2,328,981

                     Harmon Construction                     $2,200,000                     $39,000                     $99,000                     $2,338,000

                     National CB                     $2,180,773                     $90,200                     $88,780                     $2,359,753

                     D.F. Osborne Construction                     $2,287,500                     $55,000                     $127,300                     $2,469,800

                     Architect’s Estimate                     $2,584,573                     $45,538                     $145,000                     $2,775,111

 

This project is for the planning, design, and construction of a Fire Training Center on City-owned land approximately ½ mile north of Olathe West High School (home to the district’s Public Safety Academy). The property is bounded by City-owned land to the north, east and south, and by residential to the west. The scope will include a training “burn” tower; a small building to house restrooms, storage, office space, plus a covered outdoor classroom space; significant site improvements; and space for future small fire training “props”.

 

This contract with Crossland Construction, Inc. will construct the site improvements and the small building housing the restrooms, storage, and office space plus the covered outdoor classroom space.  On December 3, 2019, City Council approved the contract for the design, fabrication, and installation of the Fire Training Tower component of the project.

 

Three scopes of work were bid as alternates and are proposed to be included in the contract. The alternates include full site lighting, motor-operated vehicle gates and a monument sign along Hedge Lane.

 

Construction is tentatively scheduled to begin in early July 2020 with completion by the end of the year.  It is anticipated that the Fire Training Tower component of the project will be completed in Spring 2021.

_______________________________________________________________________________

Financial Impact:

Funding for the Fire Training Center Improvements Project includes:

 

CIP Funds                     $1,000,000

GO Bonds                     $3,000,000

Total                     $4,000,000

 ________________________________________________________________________________

Action Needed:

Approval of Architect’s Estimate, acceptance of bids, and award of contract to Crossland Construction, Inc. for construction of the Fire Training Center Improvements Project, PN 6-C-004-13.

________________________________________________________________________________

Attachment(s):

A.  Project Location Map

B.  Project Fact Sheet

C.  Architect’s Estimate and Affidavit of Estimate

D.  Agreement