File #: G20-1700   
Type: Council Consent Status: Agenda Ready
File created: 6/3/2020 In control: City Council
On agenda: 6/16/2020 Final action:
Title: Consideration of Change Order No. 1 to the contract with Linaweaver Construction, Inc. for construction of the 2020 Cedar Creek Streets Improvements Project, PN 3-P-003-20.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Change Order No. 1, 4. D. Resolution 19-1063

Department: Public Works

Staff Contact: Mary Jaeger / Beth Wright

Subject: Change Order No. 1 to the contract with Linaweaver Construction, Inc. for construction of the 2020 Cedar Creek Streets Improvements Project, PN 3-R-003-20.

________________________________________________________________________________

Item Description:

title

Consideration of Change Order No. 1 to the contract with Linaweaver Construction, Inc. for construction of the 2020 Cedar Creek Streets Improvements Project, PN 3-P-003-20..

________________________________________________________________________________

Summary:

On May 5, 2020, City Council awarded a contract to Linaweaver Construction, Inc. for construction of the 2020 Cedar Creek Streets Improvements Project. The amount of the contract was $800,719.00, which was below the Engineer’s Estimate of $895,762.50. Due to the low and responsible bid submitted by Linaweaver Construction, Inc., the project budget will allow the addition of alternate streets. These alternate streets were approved as part of Resolution 19-1063, authorizing the 2020 Street Reconstruction Program and can be seen on the attached Project Location Map.

 

Change Order No. 1, in the amount of $171,297.00, will include full removal of current concrete streets and replacement with subgrade improvements, full depth asphalt pavement, replacement of concrete curb and gutters, and spot replacement of existing sidewalk and driveway approaches as required for one additional street:

 

1)                     W. 104th Terrace, Cedar Creek Parkway to the east ends of the street.

 

Construction began June 2, 2020 and will be completed in October 2020.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2020 Street Reconstruction Program authorized on November 5, 2019. Authorized revenue for the 2020 Street Reconstruction Program includes:                     

 

General Obligation Bonds                                                                                                              $  5,100,000

Total                                                                                                                                                        $  5,100,000

________________________________________________________________________________

Action Needed:

Approval of Change Order No. 1 to the contract with Linaweaver Construction, Inc. for construction of the 2020 Cedar Creek Streets Improvements Project, PN 3-P-003-20.