Title: Consideration of Engineer’s Estimate, acceptance of bids and award of contract to VF Anderson Builders, LLC for construction of the Downtown Streets Improvement Project (Phase 2), Spruce Street: Kansas to Mill Creek, Chestnut Street: Santa Fe to Poplar, Cherry Street: Spruce to Mill Creek, PN 3-R-001-21.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Engineer's Estimate and Affidavit of Estimate, 4. D. Construction Agreement

focus area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with VF Anderson Builders, LLC for construction of the Downtown Streets Improvement Project (Phase 2), Spruce Street: Kansas to Mill Creek, Chestnut Street: Santa Fe to Poplar, Cherry Street: Spruce to Mill Creek, PN 3-R-001-21.

________________________________________________________________________________

Item Description:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to VF Anderson Builders, LLC for construction of the Downtown Streets Improvement Project (Phase 2), Spruce Street: Kansas to Mill Creek, Chestnut Street: Santa Fe to Poplar, Cherry Street: Spruce to Mill Creek, PN 3-R-001-21..

________________________________________________________________________________

Summary:

On January 5, 2021, seven (7) bids were received and opened for the above referenced project. The bids ranged from $1,317,228.60 to $1,784,838.50 with the Engineer’s Estimate at $1,584,601.00. VF Anderson Builders, LLC submitted the low and responsible bid in the amount of $1,317,228.60. The following is a tabulation of the bids received:

 

VF Anderson Builders, LLC                                                     $ 1,317,228.60

Kansas Heavy Construction, LLC                                                     $ 1,366,138.35

Miles Excavating Inc.                                                                          $ 1,498,404.48

Amino Brothers Co., Inc.                                                                    $ 1,499,792.30

Engineer’s Estimate                                                                                                      $ 1,584,601.00

Gunter Construction Company                                                     $ 1,639,744.45

J.M. Fahey Construction Company                                              $ 1,644,798.85

Pyramid Excavation & Construction, Inc.                                          $ 1,784,838.50

 

This Street Reconstruction project on Spruce Street, Chestnut Street and Cherry Street will include full depth asphalt pavement and subgrade replacement, replacement of concrete curb and gutters, replacement of sidewalk, driveway approaches, the addition of a westbound right turn lane on Spruce Street at Kansas Avenue, street light installation and stormwater improvements.

 

Construction is tentatively scheduled to begin in April 2021 and tentatively scheduled to be completed in November 2021.

________________________________________________________________________________

Financial Impact:

Funding for the Downtown Streets Improvement Project includes:                     

 

2021 Street Reconstruction Program                                                                    $  2,150,000

Water & Sewer Funds                                                                                                           $     120,000

Johnson County Interlocal Agreement                                                               $     684,350

Total                                                                                                                                                        $  2,954,350

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to VF Anderson Builders, LLC for construction of the Downtown Streets Improvement Project (Phase 2), Spruce Street: Kansas to Mill Creek, Chestnut Street: Santa Fe to Poplar, Cherry Street: Spruce to Mill Creek, PN 3-R-001-21.

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Project Fact Sheet

C.                     Engineer’s Estimate and Affidavit of Estimate

D.                     Construction Agreement