Title: Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Phoenix Concrete, LLC for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group A, PN 3-P-004-21.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Construction Agreement, 4. D. Engineer's Estimate and Affidavit of Estimate

focus area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with Phoenix Concrete, LLC for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group A, PN 3-P-004-21.

________________________________________________________________________________

Item Description:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Phoenix Concrete, LLC for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group A, PN 3-P-004-21..

________________________________________________________________________________

Summary:

On January 14, 2021, three (3) bids were received and opened for the above referenced project.  The bids ranged from $2,446,224.96 to $2,832,354.50 with the Engineer’s Estimate at $2,466,632.40. Phoenix Concrete, LLC submitted the low and responsible bid in the amount of $2,446,224.96. The following is a tabulation of the bids received:

 

Phoenix Concrete, LLC                                                                                    $ 2,446,224.96

Engineer’s Estimate                                                                                                         $ 2,466,632.40

Freeman Concrete Construction, LLC                                          $ 2,611,545.24

McAnany Construction, Inc.                                                               $ 2,832,354.50

 

This Street Preservation project will provide a 2” depth mill and asphalt overlay, spot replacement of concrete curb and sidewalk, installation of ADA sidewalk ramps and replacement of pavement markings on thirty-three (33) local and collector streets.

 

Construction is scheduled to begin in Spring 2021 and will be completed in Fall 2021.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2021 Street Preservation Program authorized on January 5, 2021. Authorized revenue for the 2021 Street Preservation Program includes:                     

 

G.O. Bonds                                                                                                                                                   $  4,200,000

Street Maintenance Sales Tax                                                                                    $11,000,000

Total                                                                                                                                                        $15,200,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to Phoenix Concrete, LLC for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group A, PN 3-P-004-21.

________________________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Construction Agreement

D. Engineer’s Estimate and Affidavit of Estimate