File #: G21-2126   
Type: Council Consent Status: Passed
File created: 1/20/2021 In control: City Council
On agenda: 2/2/2021 Final action: 2/2/2021
Title: Consideration of Professional Services Agreement with HDR Engineering, Inc., for design services for the 119th Street, Woodland to Northgate, Improvements Project, PN 3-C-024-21.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Professional Services Agreement

focus area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Beth Wright

Subject: Professional Services Agreement with HDR for concept and preliminary engineering of the 119th Street, Woodland to Northgate, Improvements Project, PN 3-C-024-21.

________________________________________________________________________________

Item Description:

   Consideration of Professional Services Agreement with HDR Engineering, Inc., for design services for the 119th Street, Woodland to Northgate, Improvements Project, PN 3-C-024-21.

________________________________________________________________________________

Summary:

This project is needed to provide a missing link of 119th Street between Woodland Road and Northgate, to provide total transportation connectivity from K-7 Highway, reduce congestion on adjacent arterials, and to promote commercial growth and development along the 119th Street corridor.  The project will include a new 4-lane divided arterial section along with intersection improvements at Woodland Road and 119th, Northgate and 119th Street, and Nelson and Northgate.  Also included in the scope of the project will be a bridge that spans the BNSF railroad and Mill Creek.  This project will provide pedestrian accommodations and a connection from 119th Street to the Gary Haller Trail. 

 

This project has been identified as a near term priority project in the Transportation Master Plan.  The project is also a high priority for the development community based on stakeholder meetings since it will promote commercial growth along the 119th Street corridor and connectivity between I-35 and K-7 Highway.  According to DirectionFinder Survey, the top priority of citizens is traffic flow and congestion management, with ease of east-west travel being one of the most important transportation measures. 

 

A Request for Qualifications for this project was issued on October 19, 2020. Seven (7) firms responded to this request and HDR Engineering, Inc. (HDR) was selected based on the submitted qualifications.  The proposed agreement with HDR includes traffic analysis, data collection, conceptual design alternatives, preliminary design and economic analysis.  The total cost for this agreement is $1,115,796.

 

Staff will return to council in the future with a supplemental agreement for final design.

 

This project is tentatively scheduled for design in 2021/2022, land acquisition and utility relocations in 2022, and construction in 2023/2024.

 

________________________________________________________________________________

Financial Impact:

Funding for this first phase of the 119th Street, Woodland to Northgate, Improvements Project includes:                     

                                          

GO Bonds                                                                                                         $1,800,000

Total                                                                                                    $1,800,000

________________________________________________________________________________

Action Needed:

Approval of Professional Services Agreement with HDR Engineering, Inc., for design services for the 119th Street, Woodland to Northgate, Improvements Project, PN 3-C-024-21.

______________________________________________________________________                     

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Professional Services Agreement