File #: G21-2155   
Type: Council Consent Status: Agenda Ready
File created: 2/2/2021 In control: City Council
On agenda: 2/16/2021 Final action:
Title: Consideration of Engineer’s Estimate, acceptance of bids and award of contract to McAnany Construction, Inc. for construction of the 2021 Local and Collector Street Mill and Overlay Project – Group B, PN 3-P-005-21.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Construction Agreement, 4. D. Engineer's Estimate and Affidavit of Estimate

FOCUS AREA: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with McAnany Construction, Inc. for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group B, PN 3-P-005-21.

________________________________________________________________________________

Item Description:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to McAnany Construction, Inc. for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group B, PN 3-P-005-21..

________________________________________________________________________________

Summary:

On February 4, 2021, four (4) bids were received and opened for the above referenced project. The bids ranged from $2,441,024.80 to $2,551,968.85 with the Engineer’s Estimate at $2,462,419.50. McAnany Construction, Inc. submitted the low and responsible bid in the amount of $2,441,024.80. The following is a tabulation of the bids received:

 

McAnany Construction, Inc.                                                                       $ 2,441,024.80

Phoenix Concrete, LLC                                                                          $ 2,443,373.66

Engineer’s Estimate                                                                                               $ 2,462,419.50

Freeman Concrete Construction, LLC                                $ 2,513,265.62

Kansas Heavy Construction, LLC                                                                   $ 2,551,968.85

 

This Street Preservation project will provide a 2” depth mill and asphalt overlay, spot replacement of concrete curb and sidewalk, installation of ADA sidewalk ramps and replacement of pavement markings on forty-seven (47) local and collector streets.

 

Construction is tentatively scheduled to begin in Spring 2021 and tentatively scheduled to be completed in Fall 2021.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2021 Street Preservation Program authorized on January 5, 2021. Authorized revenue for the 2021 Street Preservation Program includes:                     

 

G.O. Bonds                                                                                                                                                        $  4,200,000

Street Maintenance Sales Tax                                                                                         $ 11,000,000

Total                                                                                                                                                        $ 15,200,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to McAnany Construction, Inc. for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group B, PN 3-P-005-21.

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Project Fact Sheet

C.                     Construction Agreement

D.                     Engineer’s Estimate and Affidavit of Estimate