File #: G21-2230   
Type: Council Consent Status: Agenda Ready
File created: 3/23/2021 In control: City Council
On agenda: 4/6/2021 Final action:
Title: Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Superior Bowen Asphalt Company, LLC for construction of the Old 56 Arterial Mill and Overlay Project, PN 3-P-001-20.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Construction Agreement, 4. D. Engineer's Estimate and Affidavit of Estimate

FOCUS AREA: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with Superior Bowen Asphalt Company, LLC for construction of the Old 56 Arterial Mill and Overlay Project, PN 3-P-001-20.

________________________________________________________________________________

Item Description:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Superior Bowen Asphalt Company, LLC for construction of the Old 56 Arterial Mill and Overlay Project, PN 3-P-001-20..

________________________________________________________________________________

Summary:

On March 23, 2021, two (2) bids were received and opened for the above referenced project. The bids ranged from $1,430,401.15 to $1,634,999.99 with the Engineer’s Estimate at $1,423,983.50. Superior Bowen Asphalt Company, LLC submitted the low and responsible bid in the amount of $1,430,401.15. The following is a tabulation of the bids received:

 

Engineer’s Estimate                                                                                                             $ 1,423,983.50

Superior Bowen Asphalt Company, LLC                                                  $ 1,430,401.15

McAnany Construction, Inc.                                                     $ 1,634,999.99

 

This Street Preservation project will provide a 2” mill and asphalt overlay on Old 56 Highway from Lone Elm Road to 151st Street. This project will also include shoulder improvements, ADA ramp installation at the Robinson Drive intersection, traffic signal detection improvements, and pavement markings. Additionally, work will occur connecting Old 56 Highway to the City of Olathe Parks and Recreation maintenance facility with an asphalt entrance road including concrete curb and gutter installation, streetlights, and widening on Old 56 Highway to accommodate turn lanes.

 

Construction is tentatively scheduled to begin in Spring 2021 and tentatively scheduled to be completed in Fall 2021.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2020 Street Preservation Program authorized on January 7, 2020. Authorized revenue for the 2020 Street Preservation Program includes:                     

 

CIP Fund Cash                                                                                                                                   $   2,200,000

CPR Fund Cash                                                                                                                                   $      800,000

G.O. Bonds                                                                                                                                                        $   1,000,000

Street Maintenance Sales Tax                                                                                         $   9,000,000

Street Maintenance Sales Tax                                                                                         $      600,000

Total                                                                                                                                                        $ 13,600,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to Superior Bowen Asphalt Company, LLC for construction of the Old 56 Arterial Mill and Overlay Project, PN 3-P-001-20.

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Project Fact Sheet

C.                     Construction Agreement

D.                     Engineer’s Estimate and Affidavit of Estimate