File #: G21-2234   
Type: Council Consent Status: Agenda Ready
File created: 3/23/2021 In control: City Council
On agenda: 4/6/2021 Final action:
Title: Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Kansas Heavy Construction, LLC for construction of the Upper Cedar Creek Stormwater Improvements Project, PN 2-C-013-19.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Project Fact Sheet, 3. C. Engineer's Estimate and Affidavit of Estimate, 4. D. Construction Agreement

FOCUS AREA: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Beth Wright

Subject: Contract with Kansas Heavy Construction, LLC for construction of the Upper Cedar Creek Stormwater Improvements Project, PN 2-C-013-19.

________________________________________________________________________________

Item Description:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Kansas Heavy Construction, LLC for construction of the Upper Cedar Creek Stormwater Improvements Project, PN 2-C-013-19..

________________________________________________________________________________

Summary:

On March 15, 2021, five (5) bids were received and opened for the above referenced project. The bids ranged from $1,522,327.00 to $1,812,752.00 with the Engineer’s Estimate at $1,502,616.00. Kansas Heavy Construction, LLC submitted the low and responsible bid in the amount of $1,522,327.00. The following is a tabulation of the bids received:

 

Engineer’s Estimate                                                                                                         $1,502,616.00

Kansas Heavy Construction, LLC                                                               $1,522,327.00

Linaweaver Construction, Inc.                                                               $1,555,657.25

VF Anderson Builders, LLC                                                               $1,571,597.00

Wiedenmann, Inc.                                                                                                         $1,735,977.00

Infrastructure Solutions, LLC                                                               $1,812,752.00

 

This project includes replacement of existing corrugated metal pipe (CMP) culverts with larger concrete culverts, reconstruction of street pavement, channel improvements, storm sewer improvements, and the reduction of the flood risk for two (2) businesses identified within the 100-year floodplain through project improvements.

 

This is the second of six identified neighborhood flood control projects located outside the FEMA regulated floodplain.

 

Construction is tentatively scheduled to begin in Spring 2021 with completion in Fall 2021.

________________________________________________________________________________

Financial Impact:

Funding for the Upper Cedar Creek Stormwater Improvements Project includes:

 

Johnson County SMAC Program                                          $1,350,570

Olathe Stormwater Funds                                                               $1,184,430

Total                                                                                         $2,535,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to Kansas Heavy Construction, LLC for construction of the Upper Cedar Creek Stormwater Improvements Project, PN 2-C-013-19.

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Project Fact Sheet

C.                     Engineer’s Estimate and Affidavit of Estimate

D.                     Construction Agreement