File #: G21-2244   
Type: Council Consent Status: Agenda Ready
File created: 3/27/2021 In control: City Council
On agenda: 4/6/2021 Final action:
Title: Consideration of Change Order No. 1 to the contract with McAnany Construction, Inc., for construction of the 2021 Local and Collector Street Mill and Overlay Project – Group B, PN 3-P-005-21.
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. A. Project Location Map, 2. B. Change Order No 1

FOCUS AREA: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Consideration of Change Order No. 1 to the contract with McAnany Construction, Inc. for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group B, PN 3-P-005-21.

________________________________________________________________________________

Item Description:

title

Consideration of Change Order No. 1 to the contract with McAnany Construction, Inc., for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group B, PN 3-P-005-21..

________________________________________________________________________________

Summary:

This Change Order will allow for a 2” mill and asphalt overlay, base repair and crack repair (as needed) of the City-owned parking lot south of Loula Street and west of Kansas Avenue. The pavement is in poor condition, and the parking lot will be the new location for solid waste recycling containers for residents to access.

 

Staff compared the price from McAnany’s contract for the 2021 Local and Collector Street Mill and Overlay Project - Group B to the prices in our Price Agreement for Asphalt Trail Repairs with Updike Paving Corporation.  The prices in the contract with McAnany provided for the least expensive repair project for the parking lot. 

 

Change Order No. 1 is for $113,966.10.  Although this is a Change Order to a Contract for a Street Preservation Program project, the parking lot repairs will be funded from the 2021 Facility & Parking Lot Improvements & Maintenance Project.

 

It is anticipated that construction will occur in Spring 2021.

 

________________________________________________________________________________

Financial Impact:

These parking lot repairs will be funded from the 2021 Facility & Parking Lot Improvements & Maintenance Project.  Funding, as approved in the 2021-2025 Capital Improvement Plan, includes:

                                          GO Bonds                                                                                    $400,000

                                          Total                                                                                                          $400,000

 

________________________________________________________________________________

Action Needed:

Approval of Change Order No. 1 to the contract with McAnany Construction, Inc., for construction of the 2021 Local and Collector Street Mill and Overlay Project - Group B, PN 3-P-005-21.

________________________________________________________________________________

Attachment(s):

A.                     Project Location Map

B.                     Change Order No. 1