Type: Council Consent Status: Passed
File created: 12/21/2023 In control: City Council
On agenda: 1/9/2024 Final action: 1/9/2024
Title: Consideration of Engineer's Estimate, acceptance of bids and award of contract to Pyramid Contractors, Inc. for construction of the 119th Street Improvements Project, PN 3-P-007-23.
Staff Contact: Mary Jaeger, Nate Baldwin
Attachments: 1. A Project Location Map, 2. B. Project Fact Sheet, 3. C. Construction Agreement, 4. D. Engineer's Estimate and Affidavit of Estimate

Focus Area: Infrastructure (Engineering)

Staff Contact: Mary Jaeger / Nate Baldwin

Subject: Contract with Pyramid Contractors, Inc. for construction of the 119th Street Improvements Project, PN 3-P-007-23.

________________________________________________________________________________

TITLE:

title

Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Pyramid Contractors, Inc. for construction of the 119th Street Improvements Project, PN 3-P-007-23.

 

Body

________________________________________________________________________________

Summary:

On December 19, 2023, five (5) bids were received and opened for the above referenced project. The bids ranged from $1,847,602.20 to $2,459,163.95 with the Engineer’s Estimate at $2,809,826.00. Pyramid Contractors, Inc. submitted the low and responsible bid in the amount of $1,847,602.20. The following is a tabulation of bids received:

 

Pyramid Contractors, Inc.                                                                                    $1,847,602.20

                                          Linaweaver Construction, Inc.                                                               $1,861,571.50                     

                                          VFA Builders                                                                                                                              $1,897,966.29

                                          Kansas Heavy Construction, LLC                                                               $2,071,878.65

J.M. Fahey Construction Company                                          $2,459,163.95

Engineer’s Estimate                                                                                                         $2,809,826.00

 

This Street Preservation Project will include pavement improvements along 119th Street from Clare Road west to the Cedar Creek Wastewater Treatment Plant, construction of an 8-foot concrete sidewalk from Clare Road to the Cedar Niles Trailhead, and a 5-foot sidewalk on the east side of Clare Road from 119th Street to 127th Street.

 

Construction is tentatively scheduled to begin in Spring 2024 and tentatively scheduled to be completed in Fall 2024.

________________________________________________________________________________

Financial Impact:

This project is funded from the City of Olathe’s 2024 Street Preservation Program. Funding for the 2024 Street Preservation Program, as approved in the 2024-2028 Capital Improvement Plan, includes:      

CIP Fund (Cash)                                                               $  2,800,000

Transportation Sales Tax                                          $20,160,000

Total:                                                                                                         $22,960,000

________________________________________________________________________________

Action Needed:

Approval of Engineer’s Estimate, acceptance of bids and award of contract to Pyramid Contractors, Inc. for construction of the 119th Street Improvements Project, PN 3-P-007-23.

 

________________________________________________________________________________

Attachment(s):

A. Project Location Map

B. Project Fact Sheet

C. Construction Agreement

D. Engineer’s Estimate and Affidavit of Estimate