Skip to main content
City of Olathe header
File #: G19-511   
Type: Council Consent Status: Passed
File created: 1/7/2019 In control: City Council
On agenda: 1/22/2019 Final action: 1/22/2019
Title: Consideration of Supplemental Agreement No. 1 with TREKK Design Group, LLC. for design of the Sanitary Sewer Rehabilitation Project, PN 1-R-000-19, and the Neighborhood Sanitary Sewer Improvements Project, PN 1-R-100-19
Staff Contact: Mary Jaeger, Beth Wright
Attachments: 1. Attachment A Supplemental Agreement No 1, 2. Attachment B Project Fact Sheet

Department: Public Works

Staff Contact: Mary Jaeger/Beth Wright

Subject: Supplemental Agreement with TREKK Design Group, LLC for design services for the Sanitary Sewer Rehabilitation Project, PN 1-R-000-19, and the Neighborhood Sanitary Sewer Improvements Project, PN 1-R-100-19.

________________________________________________________________________________

Item Description:

title

Consideration of Supplemental Agreement No. 1 with TREKK Design Group, LLC. for design of the Sanitary Sewer Rehabilitation Project, PN 1-R-000-19, and the Neighborhood Sanitary Sewer Improvements Project, PN 1-R-100-19..

Body

________________________________________________________________________________

Summary:

These projects are in place to rehabilitate existing sanitary sewers that are in poor structural condition, resulting in a reduction of inflow and infiltration (I&I) and lower operational and maintenance costs.

 

On January 9, 2018, the City Council approved a Master Agreement for Professional Services with TREKK Design Group, LLC to provide design services for the Sanitary Sewer Rehabilitation and Neighborhood Sanitary Sewer Improvements Projects.  This Supplemental Agreement No. 1 will allow for completion of design services for the 2019 calendar year on an as-needed basis.  Services include design of multiple rehabilitation projects for in-house construction crews, flow monitoring of various sanitary sewer sub-basins, and investigation of neighborhood sanitary sewers in poor condition.  Additionally, services may include survey of existing conditions, utility coordination, cost estimates, land acquisition documentation needed for right-of-way or easements (title reports, easement documents, etc.), development of full construction plans and assistance with bidding of construction projects

 

The total fee for the additional professional services provided with this Supplemental Agreement is $150,000.00, which raises the total fee for all design services provided under the Master Agreement from $150,000.00 to $300,000.00.

 

The project is scheduled to begin design in January 2019 with construction occurring throughout the year.

________________________________________________________________________________

Financial Impact:

Funding for the Sanitary Sewer Rehabilitation and the Neighborhood Sanitary Sewer Improvements Projects, as approved in the 2019 Capital Improvement Plan, includes:

 

Sanitary Sewer Rehabilitation (1-R-000-19):                                          SDF Funds                                          $   500,000

                                                                                                                                                                        Water/Sewer Fund                     $   500,000

                                                                                                                                                                        Total:                                                               $1,000,000

                     

Neighborhood Sanitary Sewer Improvements                                          Revenue Bonds                     $   400,000

(1-R-100-19):                                                                                                                              Water/Sewer Fund                     $     50,000

                                                                                                                                                                        Total:                                                               $   450,000

________________________________________________________________________________

Action Needed:

Approval of Supplemental Agreement No. 1 with TREKK Design Group, LLC. for design of the Sanitary Sewer Rehabilitation Project, PN 1-R-000-19, and the Neighborhood Sanitary Sewer Improvements Project, PN 1-R-100-19.

________________________________________________________________________________

Attachment(s):

A:  Supplemental Agreement No. 1

B:  Project Fact Sheet